JAPAN ATOMIC INDUSTRIAL FORUM, INC.

for Japanese

ATOMS in JAPAN

8 November, 2017

Fuel Removal System Leaves Yokohama, Headed for Fukushima Daiichi-3

In July, the Tokyo Electric Power Co. (TEPCO) began the assembly of a domed roof for Unit 3 of its Fukushima Daiichi Nuclear Power Plants, in preparation for the removal of debris and fuel from the reactor's spent fuel pool. The roof is intended to provide a cover for the fuel removal efforts. On November 2, the fifth of eight roof units was lifted to the upper floor of the reactor building.

The vessel leaves the port at dawn for the Fukushima Daiichi NPS (photo provided by Toshiba Corporation).

Before the roof can be completed, though, a fuel removal system (FRS) must first be installed on the operating floor at the top of the reactor building. On November 5, the system was shipped from Honmoku Pier in Yokohama port, located along Tokyo Bay.

The FRS consists of both a fuel handling machine (FHM) and a crane. The FHM is designed to remove debris and fuel from the spent fuel pool in a safe and secure manner, as well as to minimize radiation exposure. Operations to remove the debris and fuel can be monitored by cameras installed on two manipulators. Various auxiliary tools (such as cables, rebar-cutting devices, and grippers) can be installed at the tip of each manipulator.

After the fuel is removed from the pool, it will be placed in a transfer vessel, lifted by crane, and moved to a ground-level floor of the reactor building for transportation to a temporary storage site.

Using multiple cameras and other devices, the FRS will be remotely operated from a building near the Main Anti-Earthquake Building: an approach not seen in the past. Toshiba Energy Systems & Solutions Corporation, which made the system, carried out extensive testing and training of operators before it shipped the FRS to the Fukushima Daiichi NPPs.

FHM (foreground) and crane are loaded onto a vessel at the port (photo provided by Toshiba Corporation).

After arrival, the FRS will be installed at Unit 3 around the middle of this month.

According to the schedule announced by TEPCO, the installation of the dome will be completed in early fiscal 2018 (starting in April of next year) and removal will begin about around October or so.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)

23 January, 2020
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)07:47

Recent News

30 June, 2020
“Existing NPPs to Enter Age of 80-Year Operations” JAIF Annual Survey Says
16 June, 2020
Toshiba ESS and Yokohama National University Boost Joint Research to Upgrade Heavy-Ion Cancer Therapy, Using Kanagawa Prefectural Facility
8 June, 2020
NRA Grants Permission to Make Changes to Reactor Installation at HTTR under New Regulatory Standards
22 May, 2020
Sendai-2 Starts Periodic Inspection, with Due Date Imminent to Install Specific Safety Facilities
15 May, 2020
NRA Issues Draft Review Report for Rokkasho Reprocessing Plant
30 April, 2020
Construction Begins of Next Generation Synchrotron Radiation Facility at Tohoku University, to Be Used for Fuel Cells and Pharmaceuticals
27 April, 2020
Superconducting-Coil Tokamak Plasma Test Device (JT-60SA) Installed at Naka Fusion Institute, with Plasma Generation to Begin in Autumn
17 April, 2020
Japan’s CO2 Emissions Fall 4.6% in FY18, Thanks in Part to Restart of NPPs
14 April, 2020
ANRE Begins Hearing from Concerned Parties on Handling of Treated Contaminated Water at Fukushima Daiichi NPPs
14 April, 2020
IAEA Issues Report Reviewing Treated Contaminated Water at Fukushima Daiichi NPPs, Praising Earlier ANRE Report
▲TOP