Fukushima Daiichi Frozen Wall Tests Succeed in Lowering Underground Temperatures to 15 Degrees below Zero

On May 14, the Tokyo Electric Power Co. (TEPCO) announced that its tests of frozen-soil shielding walls had succeeded in lowering temperatures underground to as low as 15 degrees zero (C). The walls are aimed at dealing with the contaminated water coming from the Fukushima Daiichi Nuclear Power Station, damaged in the March 2011 earthquake.

The frozen-soil shielding wall project aims to freeze the ground at a depth of 30m deep, to a temperature of 30 degrees below zero (C). According to TEPCO, it is unclear how much soil is actually frozen now.

At one of the 18 points on the west side of the reactor buildings (i.e., away from the sea) where TEPCO began testing on April 30, the temperature of the soil some 40cm from a coolant pipe was measured at 15 degrees below zero (C) on May 13, or some 25 degrees colder than when the freezing operation began.

At the same time, however, there were multiple points where significant changes in temperature were not observed. TEPCO considers that to have been at least partially due to the thermometers being too far from the coolant pipes.

Trying to explain that, TEPCO representatives said, “The equipment was confirmed to be working properly, so we want to evaluate how the ground is freezing based on measurement data over a longer period.”

The frozen-soil shielding wall effort involves circulating a coolant in pipes installed across an area surrounding the buildings at Fukushima Daiichi measuring some 1.5km, and then freezing the ground to stop the inflow of groundwater to the buildings, while also preventing contaminated water from the reactor complex reaching the outside.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)

23 January, 2020
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)07:47

Recent News

29 January, 2020
JAIF President Takahashi Gives Press Briefing, Describing Court Order Halting the Operation of Ikata-3 as “Regrettable”
23 January, 2020
Finishing Mission in Japan, IAEA’s IRRS Points Out Importance of NRA’s Communicating with Nuclear Industry
21 January, 2020
Evacuation Orders for Futaba, Okuma, Tomioka Towns to Be Partially Lifted in March, with JR Joban Line to Be Completely Reopened for Service
16 January, 2020
Japan’s Nuclear Power Plant Capacity Factor Stood at Just 21.4 Percent Last Year
26 December, 2019
IEEJ’s Supply-Demand Outlook for FY2020 Looks at Effect of Specific Safety Facility Installation Deadlines
25 December, 2019
ANRE Committee Clarifies Options for Treated Contaminated Water at Fukushima Daiichi NPPs, Viewing Both Offshore and Vapor Release Favorably
24 December, 2019
Fuel Removal from Fukushima Daiichi-1 NPP: Large Cover to be Installed First
18 December, 2019
JAEC Begins Hearing from University Personnel on Human Resource Development, Starting with Nagoya and Osaka Universities
13 December, 2019
NRA Approves Decommissioning Plans for Kansai EP’s Ohi-1 and-2
12 December, 2019
JAEA Holds International Forum on Peaceful Use of Nuclear Energy, Nuclear Non-Proliferation and Nuclear Security
▲TOP