Kansai EP Appeals District Court Decision Halting Operation of Takahama-3 and -4

On April 14, after the decision by the Fukui District Court ordering a temporary injunction halting the operation of Units 3 and 4 at the Takahama Nuclear Power Station (PWRs, 870 MWe each), Kansai Electric Power Co. (Kansai EP) swiftly decided to initiate an appeal after reviewing the details of the judgment. Also, the power company released a comment announcing that it would continue striving its utmost to demonstrate and verify the safety of the reactors, so as to minimize the effects of the recent court decision on the procedure leading to their restart.

Takahama-3&4

In February of this year, Kansai EP had received a permit from the Nuclear Regulation Authority (NRA) to change nuclear installations at the site, as it was determined that the two reactors conformed to new regulatory standards. Ever since a petition was filed with the Fukui District Court last December seeking an injunction to halt the reactors’ operation, the power company has been seeking its dismissal. At the same time, Kansai-EP has been demonstrating that the safety of the two units is secured based on scientific and professional grounds, including the explanations it has made at review meetings held by the NRA.

The two Takahama units are not the only reactors owned by Kansai EP facing a lawsuit. In May 2014, the same Fukui District Court handed down a judgment recognition a petition to halt operation of Ohi-3 & -4, with Kansai EP appealing the judgment the very next day.

At the April 14 session of the annual conference of the Japan Atomic Industrial Forum, Inc. (JAIF), Akihiro Sawa of The 21st Century Public Policy Institute cited the problem of the “lack of regulatory transparency” surrounding nuclear power in Japan, speaking in reference to news reports of the two Takahama units. He added, “The risk of lawsuits is especially growing larger.”

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

Grossi on Fukushima: Marking a Decade Since the Accident

10 March, 2021
Grossi on Fukushima: Marking a Decade Since the Accident04:11

Recent News

13 January, 2022
METI Minister Hagiuda Discusses U.S. Nuclear Cooperation, Winter Electricity Supply and Demand
27 December, 2021
TEPCO Submits Application to NRA for Facilities to Deal with ALPS-Treated Water at Fukushima Daiichi
18 November, 2021
METI Minister Speaks to IAEA International Conference on Decade of Progress Since Fukushima Daiichi Accident
15 November, 2021
Nuclear Energy’s Contribution to Achieving SDGs
8 November, 2021
COP26: Prime Minister Kishida Announces Additional Contribution of USD10 Billion for Climate Change Measures
30 October, 2021
Reelection of Suttsu Mayor Means Literature Investigation for HLW Disposal Will Continue
21 October, 2021
Kishida Makes First Visit to Fukushima Since Becoming Prime Minister
15 October, 2021
LDP Adds SMR Development and Nuclear Fusion to NPP Restarts in Its Policy Manifesto
7 October, 2021
Kishida Administration Inaugurated, with New METI Minister Hagiuda Holding Press Conference on Taking Office
6 October, 2021
IAEA Holds 65th General Conference in Vienna, with Japanese Minister of State for Science and Technology Delivering Statement in the General Debate
30 September, 2021
JAEC Releases 2020 White Paper on Nuclear Energy
17 September, 2021
NRA Permits Shimane-2 under New Regulatory Standards
14 September, 2021
IAEA Deputy Director General Evrard Visits Japan in Advance of Safety Review of ALPS-treated Water
1 September, 2021
Evaluation Report Issued by IAEA’s Review Mission to Fukushima Daiichi: First Visit since 2018
24 August, 2021
METI and IAEA Agree on Further Review Missions to Fukushima Daiichi
4 August, 2021
JAEA Restarts High-Temperature Engineering Test Reactor “HTTR”
2 August, 2021
Information about Fukushima Daiichi NPS Water Treatment
28 July, 2021
METI’s Committee Shows Rough Draft of Next Strategic Energy Plan
2 July, 2021
Mihama-3 Restarted After Decade-long Hiatus: First Restart in Japan of a Reactor Operating Beyond 40 Years
28 June, 2021
Mihama-3 Restarts after Decade-long Hiatus
▲TOP