Current Statusin Operation
Applications for Restart2013-07-08
NRA's Approval for basic design2014-09-10
NRA's Approval for detailed design2015-03-18
NRA's Approval for safety program2015-05-27
Start of NRA Pre-service Inspection2015-03-30
Local Consent2014-11-07
Restart2015-08-11
Age:37

PWR  890MWe (gross)
          846MWe (net)

Owner:  

Operator:

Date of order:
1978
Construction Start:
1979-01
Concrete placing:
1979-12
Initial Criticality:
1983-08-25
Grid connection:
1983-09-16
Commercial Operation:
1984-07-04
Main contractor:
MHI
Architect Engineer:
MAPI
Reactor System supplier:
MHI
Reactor Vessel supplier:
MHI
Incore Structure supplier:
MHI
Fuel supplier:
MNF/NFI
Steam raising supplier:
MHI
Turbine generator supplier:
MHI
Civil works:
various
2013-07-08 2013-07-08   2014-09-10 2014-11-07 2015-08-11

New Regulatory Standards came into effect

Applications by Operator

Application for Permission to Install a Reactor
(Basic design)

NRA Approval

Local Consent
(not a legal requirement)

Restart the reactor

  2015-03-18 2015-03-30
Application for Approval of Construction Plan
(Detailed design based on basic design)

NRA Approval

Pre-service Inspection by NRA

Application for Approval of Operational Safety Program
(Matters regarding operations, including operational safety)

NRA Approval

            2015-05-27  
SNS facebooktwitter

Video

Grossi on Fukushima: Marking a Decade Since the Accident

10 March, 2021
Grossi on Fukushima: Marking a Decade Since the Accident04:11

Recent News

17 September, 2021
NRA Permits Shimane-2 under New Regulatory Standards
14 September, 2021
IAEA Deputy Director General Evrard Visits Japan in Advance of Safety Review of ALPS-treated Water
1 September, 2021
Evaluation Report Issued by IAEA’s Review Mission to Fukushima Daiichi: First Visit since 2018
24 August, 2021
METI and IAEA Agree on Further Review Missions to Fukushima Daiichi
4 August, 2021
JAEA Restarts High-Temperature Engineering Test Reactor “HTTR”
2 August, 2021
Information about Fukushima Daiichi NPS Water Treatment
28 July, 2021
METI’s Committee Shows Rough Draft of Next Strategic Energy Plan
2 July, 2021
Mihama-3 Restarted After Decade-long Hiatus: First Restart in Japan of a Reactor Operating Beyond 40 Years
28 June, 2021
Mihama-3 Restarts after Decade-long Hiatus
25 June, 2021
New Canada-Japan Partnership Supports Greater Collaboration to Meet Climate Change Objectives and Net-zero Goals