Otsu District Court Orders Halt to Operation of Takahama-3 & -4 NPPs

Deciding on a request for a temporary injunction prohibiting operation of the Takahama-3 and -4 Nuclear Power Plants (PWRs, 870MWe each), owned and operated by the Kansai Electric Power Co. (Kansai EP), filed by anti-nuclear local groups in Shiga Prefecture, District Court Judge Yoshihiko Yamamoto on March 9 ruled against their operation.

Takahama-3&4

This is the first judicial decision prohibiting operation of NPPs that had restarted after the accident at the Fukushima Daiichi Nuclear Power Plants. Because a temporary injunction is effective immediately, in contrast to the case of a ruling in a lawsuit, the two units are forced to shutdown. Unless the decision is reversed by a judicial procedure hereafter, Kansai EP may not continue resumption of operation of them.

Confusion is increasing in the circumstances around nuclear power in Japan.

On the same day, Kansai EP released a statement: “We will promptly take steps to file an objection and will do our best to assert and prove the safety of the Takahama-3 and -4 NPPs so as to obtain the lifting of the temporary injunction as soon as possible.”

Both the Takahama-3 and Takahama-4 cleared the safety examinations by the Nuclear Regulation Authority (NRA) in February 2015. Unit 3 was restarted this past January and is in operation at the moment. Unit 4 was restarted in February, but operation was suspended because of a problem occurring immediate after that. Kansai EP submitted to the NRA just today a report on the cause of that problem and the steps it would take to correct it.

Points of contention are standard ground motion (Ss), the intensity of the maximum earthquake assumed for the aseismic design, which Kansai EP put at 700 gals; and the validity of the new regulatory standards for NPPs provided by the NRA. Saying that Kansai EP’s assumption is “not sufficient to secure safety,” the local anti-nuclear group asserted that if an accident occurs, people in Shiga Prefecture would be exposed to radiation and that Lake Biwa would be contaminated to the extent of adversely affecting drinking water in the Kinki Region. They argued that the requirement under the new regulatory standards is too low and, further, that no effective evacuation plan has been issued. Kansai EP rebuts the contention vigorously, saying “safety is secured.”

Concurrently with its request for a temporary injection, the anti-nuclear-side filed a lawsuit, which is pending in same court.

Judge Yamamoto served as the chief judge in a decision on a temporary injunction regarding Takahama-3 and -4 that was made in November 2014, before the restarts. At that time he denied an injunction because restarts were not imminent.

Issues of the two units were also litigated at the Fukui District Court. In April 2015, that court issued a temporary injunction prohibiting restarts, but a different judge reversed the decision and the anti-nuclear group appealed to the Kanazawa Branch of the Nagoya District Court.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

Voices from Nuclear Industry – Contributing to a clean and resilient recovery

3 September, 2020
Voices from Nuclear Industry – Contributing to a clean and resilient recovery03:59

Recent News

26 November, 2020
JAIF Releases Results of Fact-finding Survey of Japanese Nuclear Industry for Fiscal 2019: Some Effects Seen of COVID-19
24 November, 2020
Japan’s Energy Supply and Demand in Fiscal 2019 Shows CO2 Emissions Down for Sixth Year in a Row
24 November, 2020
NUMO Accepts Applications from Two Municipalities to Conduct Literature Surveys, Moving Closer Toward Selecting HLW Final Disposal Site
16 November, 2020
Kyushu Electric Power Starts Operating Facilities at Sendai-1 NPP Designed for “Specific Severe Accident” Response—First Time in Japan
13 November, 2020
Japan’s NRA Approves Changes to Mutsu Recyclable-Fuel Storage Center after Confirming Regulatory Compliance
13 November, 2020
Keidanren Announces New Growth Strategy Supporting Advanced Reactor Development
29 October, 2020
New Prime Minister Suga Enthusiastic for Carbon-Free Society by 2050
16 October, 2020
Government’s Strategic Policy Committee Starts Deliberations toward Revision of Strategic Energy Plan
13 October, 2020
NUMO Accepts Suttsu’s Application for Literature Survey in Selecting HLW Final Disposal Site—First Since Release of Map of Scientific Features
12 October, 2020
Nuclear Power Plant and Reactor Exporters’ Principles of Conduct (NuPoC)
▲TOP