6 April, 2016

Request Denied for Order Prohibiting Operation of Sendai NPPs: “New Regulatory Standards Are Rational”

In an appeal filed by a group of local anti-nuclear residents to the Fukuoka High Court's Miyazaki branch of an earlier decision by the Kagoshima District Court refusing to issue a temporary injunction against operation of the Sendai-1 and -2 Nuclear Power Plants (PWRs, 890MWe each), the High Court – presided over by Chief Judge Tomoichiro Nishikawa – on April 6 rejected the appeal, saying that the new regulatory standards are "rational."

Sendai NPPs

The two units in Satsumasendai City, Kagoshima Prefecture, are owned and operated by the Kyushu Electric Power Co. In March, in contrast, the Otsu District Court issued an injunction prohibiting operation of the Takahama-3 and -4 NPPs, owned and operated by the Kansai Electric Power Co. (Kansai EP), in Fukui Prefecture. The decision this time means judicial opinions are split.

After the accident at TEPCO’s Fukushima Daiichi NPPs in March 2011, operation of all NPPs in Japan was suspended. After clearing an examination by the Nuclear Regulation Authority (NRA) of compatibility with the new regulatory standards requiring a tightening of safety measures, the Sendai NPPs were restarted in August 2015, ahead of the others.

The points in dispute at the appeal hearing were (1) anti-earthquake measures, (2) effects of volcanoes, and (3) effectiveness of evacuation plans, in addition to the rationality of the regulatory standards themselves.

The decision today found the regulatory standards rational, saying they were issued incorporating the lessons of the accident at the Fukushima Daiichi NPPs. As for standard ground motion (Ss) – the maximum tremors from an earthquake assumed in aseismic design – the Court noted that the NPPs were designed taking regional characteristics into consideration and that it cannot be said that standard ground motion was underestimated.

Regarding volcanic effects and evacuation of plants, the Court again recognized the NRA’s decision as appropriate, and concluded that there was “no fear of violating residents’ human rights by operation of the reactors.”

In April 2015, the Kagoshima District Court rejected a request for a temporary injunction by a group of local anti-nuclear residents and the anti-nuclear group filed an immediate appeal. The appeal hearings were concluded after two sessions.

The Kyushu Electric Power Co. released a comment stating: “The decision recognizes our argument that the safety of the Sendai NPPs is secured, and is appropriate.”

At a press conference, Japan’s Chief Cabinet Secretary Yoshihide Suga said: “The government’s stance remains the same: that NPPs whose compatibility with the new regulatory standards – among the strictest in the world – is confirmed, will be restarted with local understanding.”

Because the appeal was rejected, Kyushu Electric Power, should, through continued operation of the Sendai-1 and -2 NPPs, be able to improve its profitability, and it is likely that the company will post a net profit in March 2016 after five years of net losses. If its Genkai-3 and -4 NPPs in Saga Prefecture, for which the NRA’s examinations are in the final stage, are restarted, the company’s financial position should further improve to the point where it can embark on a reduction of power rates.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)

23 January, 2020
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)07:47

Recent News

3 August, 2020
On Taking Office as JAIF President
3 August, 2020
Nuclear Energy Buyers Guide in Japan 2020-21 is now available
31 July, 2020
Thoughts on the Decision to Approve Changes to the Reprocessing Business
31 July, 2020
NRA Permits JNFL to Alter Rokkasho Reprocessing Plant, Its Having Complied with New Regulatory Standards
30 June, 2020
“Existing NPPs to Enter Age of 80-Year Operations” JAIF Annual Survey Says
16 June, 2020
Toshiba ESS and Yokohama National University Boost Joint Research to Upgrade Heavy-Ion Cancer Therapy, Using Kanagawa Prefectural Facility
8 June, 2020
NRA Grants Permission to Make Changes to Reactor Installation at HTTR under New Regulatory Standards
22 May, 2020
Sendai-2 Starts Periodic Inspection, with Due Date Imminent to Install Specific Safety Facilities
15 May, 2020
NRA Issues Draft Review Report for Rokkasho Reprocessing Plant
30 April, 2020
Construction Begins of Next Generation Synchrotron Radiation Facility at Tohoku University, to Be Used for Fuel Cells and Pharmaceuticals
▲TOP