Saga District Court Allows Two Genkai Reactors to Resume Operation

On June 13, Japan's Saga District Court turned down a request filed by some 230 local anti-nuclear activists for a temporary injunction blocking the restart of the Genkai-3 and -4 Nuclear Power Plants (PWRs, 1180MWe each), owned and operated by the Kyushu Electric Power Co., in Genkai Town, Saga Prefecture. The court gave the following reason for its decision: "We do not recognize that the plants are lacking in terms of safety."

Genkai NPPs

The two reactor units passed safety examinations by the Nuclear Regulation Authority of Japan (NRA) in January of this year. Two months ago, then, Saga Governor Yoshiaki Yamaguchi expressed his agreement to restart both units, which are expected to resume operation in the fall.

In its recent ruling, the district court said that it recognized the rationality of the new regulatory standards for the country’s reactors, issued in the wake of the nuclear accident at Fukushima Daiichi NPPs six years ago. It subsequently said that it did find any problems in the measures established for severe accidents at either of the Genkai units, be it due to earthquake-proofing or piping deterioration.

Meanwhile, the anti-nuclear group that opposed the Genkai reactors’ restart claimed that standard ground motion (Ss)—a factor in seismic design—had been underestimated, further pointing to the increased risk of severe accidents owing to piping deterioration.

Citing the possibility of earthquakes similar to a series of quakes registering 7 (on a scale of 1 to 7) on the Japanese seismic intensity scale that struck nearby Kumamoto Prefecture on Kyushu Island in April of last year, the residents’ group argued that safety was not ensured.

Kyushu Electric Power disagreed, saying that standard ground motion (Ss) had been properly established, and that various safety measures were in place in the event of any piping abnormality.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)

23 January, 2020
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)07:47

Recent News

3 August, 2020
On Taking Office as JAIF President
3 August, 2020
Nuclear Energy Buyers Guide in Japan 2020-21 is now available
31 July, 2020
Thoughts on the Decision to Approve Changes to the Reprocessing Business
31 July, 2020
NRA Permits JNFL to Alter Rokkasho Reprocessing Plant, Its Having Complied with New Regulatory Standards
30 June, 2020
“Existing NPPs to Enter Age of 80-Year Operations” JAIF Annual Survey Says
16 June, 2020
Toshiba ESS and Yokohama National University Boost Joint Research to Upgrade Heavy-Ion Cancer Therapy, Using Kanagawa Prefectural Facility
8 June, 2020
NRA Grants Permission to Make Changes to Reactor Installation at HTTR under New Regulatory Standards
22 May, 2020
Sendai-2 Starts Periodic Inspection, with Due Date Imminent to Install Specific Safety Facilities
15 May, 2020
NRA Issues Draft Review Report for Rokkasho Reprocessing Plant
30 April, 2020
Construction Begins of Next Generation Synchrotron Radiation Facility at Tohoku University, to Be Used for Fuel Cells and Pharmaceuticals
▲TOP