14 June, 2017

Saga District Court Allows Two Genkai Reactors to Resume Operation

On June 13, Japan's Saga District Court turned down a request filed by some 230 local anti-nuclear activists for a temporary injunction blocking the restart of the Genkai-3 and -4 Nuclear Power Plants (PWRs, 1180MWe each), owned and operated by the Kyushu Electric Power Co., in Genkai Town, Saga Prefecture. The court gave the following reason for its decision: "We do not recognize that the plants are lacking in terms of safety."

Genkai NPPs

The two reactor units passed safety examinations by the Nuclear Regulation Authority of Japan (NRA) in January of this year. Two months ago, then, Saga Governor Yoshiaki Yamaguchi expressed his agreement to restart both units, which are expected to resume operation in the fall.

In its recent ruling, the district court said that it recognized the rationality of the new regulatory standards for the country’s reactors, issued in the wake of the nuclear accident at Fukushima Daiichi NPPs six years ago. It subsequently said that it did find any problems in the measures established for severe accidents at either of the Genkai units, be it due to earthquake-proofing or piping deterioration.

Meanwhile, the anti-nuclear group that opposed the Genkai reactors’ restart claimed that standard ground motion (Ss)—a factor in seismic design—had been underestimated, further pointing to the increased risk of severe accidents owing to piping deterioration.

Citing the possibility of earthquakes similar to a series of quakes registering 7 (on a scale of 1 to 7) on the Japanese seismic intensity scale that struck nearby Kumamoto Prefecture on Kyushu Island in April of last year, the residents’ group argued that safety was not ensured.

Kyushu Electric Power disagreed, saying that standard ground motion (Ss) had been properly established, and that various safety measures were in place in the event of any piping abnormality.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

Grossi on Fukushima: Marking a Decade Since the Accident

10 March, 2021
Grossi on Fukushima: Marking a Decade Since the Accident04:11

Recent News

13 January, 2022
METI Minister Hagiuda Discusses U.S. Nuclear Cooperation, Winter Electricity Supply and Demand
27 December, 2021
TEPCO Submits Application to NRA for Facilities to Deal with ALPS-Treated Water at Fukushima Daiichi
18 November, 2021
METI Minister Speaks to IAEA International Conference on Decade of Progress Since Fukushima Daiichi Accident
15 November, 2021
Nuclear Energy’s Contribution to Achieving SDGs
8 November, 2021
COP26: Prime Minister Kishida Announces Additional Contribution of USD10 Billion for Climate Change Measures
30 October, 2021
Reelection of Suttsu Mayor Means Literature Investigation for HLW Disposal Will Continue
21 October, 2021
Kishida Makes First Visit to Fukushima Since Becoming Prime Minister
15 October, 2021
LDP Adds SMR Development and Nuclear Fusion to NPP Restarts in Its Policy Manifesto
7 October, 2021
Kishida Administration Inaugurated, with New METI Minister Hagiuda Holding Press Conference on Taking Office
6 October, 2021
IAEA Holds 65th General Conference in Vienna, with Japanese Minister of State for Science and Technology Delivering Statement in the General Debate
30 September, 2021
JAEC Releases 2020 White Paper on Nuclear Energy
17 September, 2021
NRA Permits Shimane-2 under New Regulatory Standards
14 September, 2021
IAEA Deputy Director General Evrard Visits Japan in Advance of Safety Review of ALPS-treated Water
1 September, 2021
Evaluation Report Issued by IAEA’s Review Mission to Fukushima Daiichi: First Visit since 2018
24 August, 2021
METI and IAEA Agree on Further Review Missions to Fukushima Daiichi
4 August, 2021
JAEA Restarts High-Temperature Engineering Test Reactor “HTTR”
2 August, 2021
Information about Fukushima Daiichi NPS Water Treatment
28 July, 2021
METI’s Committee Shows Rough Draft of Next Strategic Energy Plan
2 July, 2021
Mihama-3 Restarted After Decade-long Hiatus: First Restart in Japan of a Reactor Operating Beyond 40 Years
28 June, 2021
Mihama-3 Restarts after Decade-long Hiatus
▲TOP