TEPCO Releases Decontaminated Groundwater Five Times into the Sea from Fukushima Daiichi

On October 1, the Tokyo Electric Power Co. (TEPCO) released a progress report on its decommissioning work at the Fukushima Daiichi Nuclear Power Plants.

the shielding wall facing the ocean

At the specialized water facility treating contaminated groundwater pumped up from subdrains (a group of wells in the vicinity of the reactor and turbine buildings), the power company started the release of treated groundwater on September 14, carrying it out five times by September 28. So far, a total of 4,025 cubic meters of water has been released, including what was pumped up starting on September 3.

After the groundwater is treated at the facility, TEPCO and a third-party organization confirm that the concentrations of radioactive materials are below the operational targets before releasing it. The power company said that it would adhere to the operational targets and try to improve water quality in the port and prevent the sea from becoming contaminated.

On September 15, TECPO completed the installation of the three of the landside shielding walls that surround Units 1 to 4 on the mountain side. Those will be frozen first before the entire freezing takes place.

As for the remaining shielding wall facing the ocean, TEPCO installed steel sheet piles at the unfinished portion on September 22 to prevent contaminated groundwater from overflowing into the sea. After treating the joints to improve the wall’s water-tightness, it will reclaim the area inside the seaward shielding wall. The goal is to complete the wall by the end of October.

Meanwhile, TECPO began removing the roof panels of the reactor cover in July before removing spent fu
el from Unit 1. Five of the six panels had been removed by the end of last month. Dust monitoring and other readings at monitoring posts showed no significant changes. The sixth panel was removed on October 5 (see photo).

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

Fukushima Daiichi Nuclear Power Station -The year in review- (March 2018 – February 2019)

8 March, 2019
Fukushima Daiichi Nuclear Power Station -The year in review- (March 2018 – February 2019)04:56

Recent News

20 May, 2019
【52nd JAIF Annual Conference】 Leader Perspective: “French Nuclear Policy and Industry Update”
20 May, 2019
【52nd JAIF Annual Conference】 Session 3: “Diversity and Possibilities for Nuclear Technology”
15 May, 2019
【52nd JAIF Annual Conference】 Session 2: “Prospects for Development of Innovative Technology”
15 May, 2019
【52nd JAIF Annual Conference】 Fukushima Daiichi Report
15 May, 2019
【52nd JAIF Annual Conference】 Session 1: “Role of Nuclear Power as a Low-Carbon Energy Source”
10 May, 2019
JT60-SA’s Core Central Solenoid Installed at QST’s Naka Fusion Institute
10 May, 2019
President of Decommissioning Company Says “Feel” from Unit 3 Will Aid Decommissioning of Other Units
10 May, 2019
Demonstration Made by MHI and IRID of Robot Arm to Remove Fuel Debris from Fukushima Daiichi
24 April, 2019
【52nd JAIF Annual Conference】 JAIF Chairman Emphasizes Urgent Need for CO2-Free Nuclear Power
24 April, 2019
Electric Power Companies Ask NRA for Understanding on Extending Grace Period for Building Anti-Terrorism Facilities at NPPs
▲TOP