16 February, 2016

TEPCO: Total Debris from Fukushima Daiichi to Reach 749,000 Cubic Meters by 2027

On February 12, the Tokyo Electric Power Co., Inc. (TEPCO) released an estimate of how much debris will be stored from the defunct Fukushima Daiichi Nuclear Power Plants by FY27 (April 2027 to March 2028). At a meeting of a working group of the Nuclear Regulation Authority (NRA) looking at waste at Fukushima Daiichi, representatives of the power company put the volume at approximately 749,000 cubic meters, assuming the continuation of current trends and circumstances.

Based on that estimate, TEPCO issued a storage management plan over the medium term to long term (around ten years). It will be compared regularly with the actual amounts of waste being generated so as to ensure an adequate storage capacity.

According to the plan, the largest portion of the approximately 400,000 cubic meters of debris expected to be generated since last summer will be some 150,000 cubic meters of debris related to contaminated water measures, including that from the installation and dismantling of tanks. The quantity of debris related to dismantling exhaust stacks will be some 12,000 cubic meters, half of which will represent an exposure dose of over 30mSv/h.

In addition to the above, there are two radioactive miscellaneous solid waste incinerators (treating as much as 7.2 tons daily) that began operation in February, and an additional incinerator (95 tons daily) that will start operation four years from now, in 2020. Together, they are expected to decrease the volume of cut trees and spent protective clothing to 145,000 cubic meters and 54,000 cubic meters, respectively.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

Fukushima Hydrogen Energy Research Field (FH2R)

9 August, 2018
Fukushima Hydrogen Energy Research Field (FH2R)01:38

Recent News

16 August, 2018
Chugoku Electric Applies for Shimane-3 Safety Examination: Second for a Reactor under Construction after Ohma NPP
16 August, 2018
International Forum on Decommissioning Fukushima Daiichi Highlights Remotely-Operated Systems
26 July, 2018
J-Village Stadium to Revert to Original Role as Soccer Training Center, Having Contributed to the Stabilization of Fukushima Daiichi
20 July, 2018
Japan-IAEA Joint Nuclear Energy Management School Opens for 2018, Developing Next Generation of Young Professionals
20 July, 2018
ANRE to Hold Explanatory Meetings and Public Hearings on Handling of Tritium Water
6 July, 2018
NRA Draft Report: Tokai-2 NPP Complies with New Regulatory Standards
6 July, 2018
Strategic Energy Plan Approved by Cabinet: FEPC Chairman Calls It “Key Policy of the Nation”
4 July, 2018
Court of Second Instance Approves Operation of Ohi NPPs
29 June, 2018
JAIF President Personally Sad to See Fukushima Daini Go
25 June, 2018
LDP Diet Caucus Delivers Strategic Energy Plan Proposal to METI Minister, Calling for Early NPP Restarts and New NPP Construction
▲TOP