[Atoms In Japan] Operating Records of Nuclear Power Plants in January BACK

Power PlantReactor
Type
Gross
Capacity
(MWe)
Avaliability FactorCapacity FactorRemarks
Operating hours [h][%]Generated
output
[MWh]
[%]
Tokai-Daini (II)BWR110050467.7541,84066.2Shutdown due to inspection of a recirculation pump.(26.Dec.2000-11.Jan.)
Tsuruga-1BWR35700.000.0Shutdown due to periodic inspection.(20.Aug.1999-)
Tsuruga-2PWR1160744100.0862,942100.0
Tomari-1PWR579744100.0430,746100.0
Tomari-2PWR579744100.0430,748100.0
Onagawa-1BWR524744100.0389,799100.0
Onagawa-2BWR825744100.0613,800100.0
Fukushima I-1BWR46000.000.0Shutdown due to periodic inspection.(21.Dec.2000-)
Fukushima I-2BWR784744100.0583,296100.0
Fukushima I-3BWR784744100.0581,95199.8
Fukushima I-4BWR784744100.0583,296100.0
Fukushima I-5BWR784744100.0583,296100.0
Fukushima I-6BWR110000.000.0Shutdown due to periodic inspection.(8.Nov.2000-)
Fukushima II-1BWR110035447.6383,78846.9Manual shutdown due to coolant trouble.(15.Jan.-)
Fukushima II-2BWR110000.000.0Shutdown due to periodic inspection.(15.Dec.2000-)
Fukushima II-3BWR1100744100.0817,95099.9
Fukushima II-4BWR1100744100.0818,400100.0
Kashiwazaki-Kariwa-1BWR1100744100.0818,400100.0
Kashiwazaki-Kariwa-2BWR110000.000.0Shutdown due to periodic inspection.(2.Dec.2000-)
Kashiwazaki-Kariwa-3BWR1100744100.0818,400100.0
Kashiwazaki-Kariwa-4BWR110060.71,2500.2Automatic Shutdown due to coolant trouble.(7.Dec.2000-)
Kashiwazaki-Kariwa-5BWR1100744100.0786,26096.1
Kashiwazaki-Kariwa-6ABWR1356744100.01,008,864100.0
Kashiwazaki-Kariwa-7ABWR135600.000.0Shutdown due to periodic inspection.(24.Dec.2000-)
Hamaoka-1BWR54000.000.0Shutdown due to periodic inspection.(18.Sep.2000-)
Hamaoka-2BWR840744100.0624,940100.0
Hamaoka-3BWR1100744100.0818,397100.0
Hamaoka-4BWR1137744100.0845,885100.0
Shika-1BWR540744100.0401,760100.0
Mihama-1PWR340744100.0252,73899.9
Mihama-2PWR50026535.6130,47435.1Shutdown due to periodic inspection.(12.Jan.-)
Mihama-3PWR826744100.0614,473100.0
Takahama-1PWR826744100.0614,474100.0
Takahama-2PWR82628938.8235,39338.3Shutdown due to periodic inspection.(13.Jan.-)
Takahama-3PWR870744100.0647,228100.0
Takahama-4PWR870744100.0647,224100.0
Ohi-1PWR1175744100.0874,100100.0
Ohi-2PWR1175744100.0874,100100.0
Ohi-3PWR1180744100.0877,830100.0
Ohi-4PWR118019326.0193,99822.1Shutdown due to periodic inspection.(14.Nov.2000-23.Jan.)
Shimane-1BWR46000.000.0Shutdown due to periodic inspection.(11.May.2000-)
Shimane-2BWR820744100.0610,079100.0
Ikata-1PWR56639653.2185,42344.0Manual shutdown due to relief valve trouble.(5.Sep.2000-)
Ikata-2PWR566744100.0421,042100.0
Ikata-3PWR890744100.0662,140100.0
Genkai-1PWR559744100.0415,734100.0
Genkai-2PWR559744100.0415,724100.0
Genkai-3PWR1180744100.0877,800100.0
Genkai-4PWR1180744100.0877,802100.0
Sendai-1PWR890744100.0662,072100.0
Sendai-2PWR89000.000.0Shutdown due to periodic inspection.(25.Dec.2000-)
Commercial Reactor
Total / Average
(Previous Month)
44917
(44917)
28,047
(30,689)
73.9
(80.9)
24,835,856
(27,284,341)
74.3
(81.6)

FugenATR165744100.0122,717100.0
Total / Average
(Previous Month)
45082
(45082)
28,791
(30,827)
74.4
(79.7)
24,958,573
(27,297,568)
74.4
(81.4)