| [Atoms In Japan] Operating Records of Nuclear Power Plants in April, 2002 |
| Power Plant | Reactor Type | Gross Capacity (MWe) | Avaliability Factor | Capacity Factor | Remarks | ||
|---|---|---|---|---|---|---|---|
| Operating hours [h] | [%] | Generated output [MWh] | [%] | ||||
| Tokai-Daini (II) | BWR | 1100 | 104 | 14.4 | 88,290 | 11.1 | Manual shoutdown due to feedwater system trouble. (3-27. Apr.) |
| Tsuruga-1 | BWR | 357 | 286 | 39.7 | 96,012 | 37.4 | Shutdown due to periodic inspection. (26.Feb.-19.Apr.) |
| Tsuruga-2 | PWR | 1160 | 720 | 100.0 | 835,102 | 100.0 | |
| Tomari-1 | PWR | 579 | 720 | 100.0 | 416,854 | 100.0 | |
| Tomari-2 | PWR | 579 | 720 | 100.0 | 416,855 | 100.0 | |
| Onagawa-1 | BWR | 524 | 720 | 100.0 | 377,280 | 100.0 | |
| Onagawa-2 | BWR | 825 | 707 | 98.2 | 559,690 | 94.2 | Shutdown due to periodic inspection. (21.Dec.2001-1.Apr.) |
| Onagawa-3 | BWR | 825 | 720 | 100.0 | 594,000 | 100.0 | |
| Fukushima I-1 | BWR | 460 | 720 | 100.0 | 331,200 | 100.0 | |
| Fukushima I-2 | BWR | 784 | 720 | 100.0 | 564,480 | 100.0 | |
| Fukushima I-3 | BWR | 784 | 720 | 100.0 | 563,792 | 99.9 | |
| Fukushima I-4 | BWR | 784 | 720 | 100.0 | 564,307 | 100.0 | |
| Fukushima I-5 | BWR | 784 | 720 | 100.0 | 564,480 | 100.0 | |
| Fukushima I-6 | BWR | 1100 | 144 | 20.0 | 151,870 | 19.2 | Shutdown due to periodic inspection. (7.Apr.- ) |
| Fukushima II-1 | BWR | 1100 | 720 | 100.0 | 792,000 | 100.0 | |
| Fukushima II-2 | BWR | 1100 | 720 | 100.0 | 788,945 | 99.6 | |
| Fukushima II-3 | BWR | 1100 | 720 | 100.0 | 792,000 | 100.0 | |
| Fukushima II-4 | BWR | 1100 | 720 | 100.0 | 792,000 | 100.0 | |
| Kashiwazaki-Kariwa-1 | BWR | 1100 | 720 | 100.0 | 792,000 | 100.0 | |
| Kashiwazaki-Kariwa-2 | BWR | 1100 | 35 | 4.9 | 22,420 | 2.8 | Shutdown due to periodic inspection. (29.Mar.-29.Apr.) |
| Kashiwazaki-Kariwa-3 | BWR | 1100 | 720 | 100.0 | 792,000 | 100.0 | |
| Kashiwazaki-Kariwa-4 | BWR | 1100 | 720 | 100.0 | 792,000 | 100.0 | |
| Kashiwazaki-Kariwa-5 | BWR | 1100 | 720 | 100.0 | 792,000 | 100.0 | |
| Kashiwazaki-Kariwa-6 | ABWR | 1356 | 720 | 100.0 | 976,320 | 100.0 | |
| Kashiwazaki-Kariwa-7 | ABWR | 1356 | 191 | 26.7 | 223,092 | 22.9 | Shutdown due to periodic inspection. (9.Apr.- ) |
| Hamaoka-1 | BWR | 540 | 0 | 0.0 | 0 | 0.0 | Manual Shutdown due to residual heat removal system trouble. (7.Nov.2001-25.Apr.) Shutdown due to periodic inspection (26.Apr.- ) |
| Hamaoka-2 | BWR | 840 | 0 | 0.0 | 0 | 0.0 | Planned shutdown. (14.Nov.2001- ) |
| Hamaoka-3 | BWR | 1100 | 720 | 100.0 | 791,999 | 100.0 | |
| Hamaoka-4 | BWR | 1137 | 720 | 100.0 | 818,619 | 100.0 | |
| Shika-1 | BWR | 540 | 448 | 62.2 | 230,951 | 59.4 | Shutdown due to periodic inspection. (2-14.Apr.) |
| Mihama-1 | PWR | 340 | 720 | 100.0 | 244,588 | 99.9 | |
| Mihama-2 | PWR | 500 | 720 | 100.0 | 359,724 | 99.9 | |
| Mihama-3 | PWR | 826 | 720 | 100.0 | 594,653 | 100.0 | |
| Takahama-1 | PWR | 826 | 720 | 100.0 | 594,647 | 100.0 | |
| Takahama-2 | PWR | 826 | 481 | 66.8 | 393,909 | 66.2 | Shutdown due to periodic inspection. (21.Apr.- ) |
| Takahama-3 | PWR | 870 | 720 | 100.0 | 626,302 | 100.0 | |
| Takahama-4 | PWR | 870 | 720 | 100.0 | 626,351 | 100.0 | |
| Ohi-1 | PWR | 1175 | 720 | 100.0 | 845,900 | 100.0 | |
| Ohi-2 | PWR | 1175 | 720 | 100.0 | 845,905 | 100.0 | |
| Ohi-3 | PWR | 1180 | 720 | 100.0 | 849,510 | 100.0 | |
| Ohi-4 | PWR | 1180 | 359 | 49.9 | 403,149 | 47.5 | Shutdown due to periodic inspection. (17.Mar.-16.Apr.) |
| Shimane-1 | BWR | 460 | 720 | 100.0 | 331,172 | 100.0 | |
| Shimane-2 | BWR | 820 | 720 | 100.0 | 590,400 | 100.0 | |
| Ikata-1 | PWR | 566 | 0 | 0.0 | 0 | 0.0 | Shutdown due to periodic inspection. (8.Feb.- ) |
| Ikata-2 | PWR | 566 | 720 | 100.0 | 408,762 | 100.3 | |
| Ikata-3 | PWR | 890 | 720 | 100.0 | 652,265 | 101.8 | |
| Genkai-1 | PWR | 559 | 720 | 100.0 | 412,922 | 102.6 | |
| Genkai-2 | PWR | 559 | 720 | 100.0 | 414,739 | 103.0 | |
| Genkai-3 | PWR | 1180 | 720 | 100.0 | 849,480 | 100.0 | |
| Genkai-4 | PWR | 1180 | 720 | 100.0 | 849,473 | 100.0 | |
| Sendai-1 | PWR | 890 | 720 | 100.0 | 647,396 | 101.0 | |
| Sendai-2 | PWR | 890 | 289 | 40.1 | 254,428 | 39.7 | Shutdown due to periodic inspection. (13.Apr.- ) |
| Commercial Reactor Total/Average (Previous Month) | 45742 (45742) | 31,126 (32,803) | 83.1 (84.8) | 27,316,233 (29,516,031) | 82.9 (86.7) | ||
| Fugen | ATR | 165 | 224 | 31.1 | 27,564 | 23.2 | Shutdown due to periodic inspection. (7.Jan.- ) |
| Total/Average (Previous Month) | 45907 (45907) | 31,350 (32,803) | 82.2 (83.2) | 27,343,797 (29,516,031) | 82.7 (86.4) | ||