Chugoku Electric Power to End Decommissioning Shimane-1 by Fiscal 2045

On April 28, Japan's Chugoku Electric Power Co. released an outline of a decommissioning plan for its Shimane-1 Nuclear Power Plant (BWR, 460MWe), located in Matsue City, Shimane Prefecture. The plant’s official decommissioning had been decided upon on April 30 of last year.

SHimane NPPs

The outline, describing the dismantling and removal processes at the reactor, says that Chugoku Electric Power will complete the decommissioning by FY45 (ending March 31, 2046). Prior to filing an application with Japan’s Nuclear Regulation Authority (NRA) for approval of the plan, the power company had given an explanation about it to the hosting municipality, Matsue City, asking that municipality for its consent.

In a visit to the office of Matsue Mayor Masataka Matsuura, Chugoku Electric Power President Mareshige Shimizu explained that the decommissioning would be carried out over 30 years, beginning in the current fiscal year. Until FY29 (ending March 31, 2030), the power company plans to prepare for dismantling work, and will also dismantle and remove peripheral reactor equipment.

The power company will launch the dismantling of the reactor itself in FY30 (ending March 31, 2031). The spent nuclear fuel assemblies are to be removed from the premises before the reactor is dismantled.

Having already requested removal of the spent fuel assemblies early on, Mayor Matsuura said, “The plan says that they will be removed at a relatively early stage, and I greatly appreciate that. I expect that the company will implement the plan steadily.”

Shimane-1 has been operated for more than 40 years. Originally, Chugoku Electric Power, Matsue City and Shimane Prefecture concluded a safety agreement on operation of NPPs and decommissioning, requiring preliminary consents of the prefecture and local municipalities before filing decommissioning applications.

In the afternoon of April 28, the power company also asked Tottori City and other adjacent cities for their preliminary consents as well.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)

23 January, 2020
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)07:47

Recent News

7 August, 2020
Nuclear Powered Ship Mutsu Designated as Special “Ship Heritage”
3 August, 2020
On Taking Office as JAIF President
3 August, 2020
Nuclear Energy Buyers Guide in Japan 2020-21 is now available
31 July, 2020
Thoughts on the Decision to Approve Changes to the Reprocessing Business
31 July, 2020
NRA Permits JNFL to Alter Rokkasho Reprocessing Plant, Its Having Complied with New Regulatory Standards
30 June, 2020
“Existing NPPs to Enter Age of 80-Year Operations” JAIF Annual Survey Says
16 June, 2020
Toshiba ESS and Yokohama National University Boost Joint Research to Upgrade Heavy-Ion Cancer Therapy, Using Kanagawa Prefectural Facility
8 June, 2020
NRA Grants Permission to Make Changes to Reactor Installation at HTTR under New Regulatory Standards
22 May, 2020
Sendai-2 Starts Periodic Inspection, with Due Date Imminent to Install Specific Safety Facilities
15 May, 2020
NRA Issues Draft Review Report for Rokkasho Reprocessing Plant
▲TOP