Decommissioning FBR Monju: Processing of Fuel Assemblies Is Underway

On December 7, the Japan Atomic Energy Agency (JAEA) reported to the Safety Monitoring Team of the Nuclear Regulation Authority (NRA) on the state of decommissioning the prototype fast breeder reactor (FBR) “Monju.”

FBR Monju

The decommissioning plan for the FBR, approved by the NRA at the end of March, comprises four stages. In the first stage, designated a period of removal of fuel (FY18 through 22), major items to be carried out include sampling of secondary system sodium, removal of fuel assemblies, and evaluations of pollution distribution.

The removal of Monju’s fuel assemblies consists of work to transfer the assemblies from the reactor core to a fuel storage tank outside the core (fuel removal), and then from that tank to a fuel pond (fuel processing and storage).

According to JAEA’s explanation at the meeting on December 7, the transfer of fuel assemblies from the tank outside the core to the fuel pond began at the end of August, but as of December 6, only 54 of the 530 assemblies had been transferred, and the target for completing processing of one hundred assemblies, which was initially set for mid-December, has been postponed until January 2019.

As of the end of November, a total of 64 “faults” or “phenomena” had occurred in the course of the work, which were corrected, with improvements reflected in the subsequent work.

Toward FY19 (starting in April 2019), when the processing of fuel assemblies will be in full swing, experience will be accumulated in maintenance related to sodium adherence. A five-team system will then be launched based on skills acquired using a three-team system.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)

23 January, 2020
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)07:47

Recent News

30 June, 2020
“Existing NPPs to Enter Age of 80-Year Operations” JAIF Annual Survey Says
16 June, 2020
Toshiba ESS and Yokohama National University Boost Joint Research to Upgrade Heavy-Ion Cancer Therapy, Using Kanagawa Prefectural Facility
8 June, 2020
NRA Grants Permission to Make Changes to Reactor Installation at HTTR under New Regulatory Standards
22 May, 2020
Sendai-2 Starts Periodic Inspection, with Due Date Imminent to Install Specific Safety Facilities
15 May, 2020
NRA Issues Draft Review Report for Rokkasho Reprocessing Plant
30 April, 2020
Construction Begins of Next Generation Synchrotron Radiation Facility at Tohoku University, to Be Used for Fuel Cells and Pharmaceuticals
27 April, 2020
Superconducting-Coil Tokamak Plasma Test Device (JT-60SA) Installed at Naka Fusion Institute, with Plasma Generation to Begin in Autumn
17 April, 2020
Japan’s CO2 Emissions Fall 4.6% in FY18, Thanks in Part to Restart of NPPs
14 April, 2020
ANRE Begins Hearing from Concerned Parties on Handling of Treated Contaminated Water at Fukushima Daiichi NPPs
14 April, 2020
IAEA Issues Report Reviewing Treated Contaminated Water at Fukushima Daiichi NPPs, Praising Earlier ANRE Report
▲TOP