JAPAN ATOMIC INDUSTRIAL FORUM, INC.

for Japanese

ATOMS in JAPAN

7 July, 2015

Fuel Loading Starts at Sendai-1 on July 7

On July 3, Japan's Nuclear Regulation Authority (NRA) completed pre-service inspections at Unit 1 of the Sendai Nuclear Power Plant, owned and operated by the Kyushu Electric Power Co., and located in Satsumasendai City of Kagoshima Prefecture. The inspections are required before nuclear fuel can be loaded into the reactor.

Sendai NPPs

Now that pre-loading procedures have been completed, Kyushu Electric Power began loading the first of 157 fuel assemblies today at Sendai-1, and will continue doing so for four days or so. The reactor is expected to resume operation in mid-August, after having been shut down in May 2011, with commercial operation to begin the following month.

The NRA began the pre-service inspections at the end of March of this year to ascertain whether the equipment and facilities at the reactor were in accordance with the results of safety examinations under new regulatory standards, as well as whether they had the necessary capabilities. All of those are preconditions for restarting NPPs in Japan.

Sendai-1 will make joint use of equipment and facilities on the side closer to Sendai-2; the final inspections completed on July 3 involved those. Meanwhile, the pre-service inspections at Sendai-1 had already been completed on June 19.

Starting today, Kyushu Electric Power intends to load about 40 fuel assemblies into the reactor daily. Three days from now, on July 10, it plans to check whether the assemblies were loaded properly. Thereafter, it will run water through piping to check for leakage. It will also conduct a drill prior to the restart so as to prevent severe accidents.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, July 2019)

8 July, 2019
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, July 2019)09:17

Recent News

23 January, 2020
Finishing Mission in Japan, IAEA’s IRRS Points Out Importance of NRA’s Communicating with Nuclear Industry
21 January, 2020
Evacuation Orders for Futaba, Okuma, Tomioka Towns to Be Partially Lifted in March, with JR Joban Line to Be Completely Reopened for Service
16 January, 2020
Japan’s Nuclear Power Plant Capacity Factor Stood at Just 21.4 Percent Last Year
26 December, 2019
IEEJ’s Supply-Demand Outlook for FY2020 Looks at Effect of Specific Safety Facility Installation Deadlines
25 December, 2019
ANRE Committee Clarifies Options for Treated Contaminated Water at Fukushima Daiichi NPPs, Viewing Both Offshore and Vapor Release Favorably
24 December, 2019
Fuel Removal from Fukushima Daiichi-1 NPP: Large Cover to be Installed First
18 December, 2019
JAEC Begins Hearing from University Personnel on Human Resource Development, Starting with Nagoya and Osaka Universities
13 December, 2019
NRA Approves Decommissioning Plans for Kansai EP’s Ohi-1 and-2
12 December, 2019
JAEA Holds International Forum on Peaceful Use of Nuclear Energy, Nuclear Non-Proliferation and Nuclear Security
29 November, 2019
NRA Issues Draft Review Report: Onagawa-2 Meets New Regulatory Standards
▲TOP