Fuel Loading Starts at Sendai-1 on July 7

On July 3, Japan's Nuclear Regulation Authority (NRA) completed pre-service inspections at Unit 1 of the Sendai Nuclear Power Plant, owned and operated by the Kyushu Electric Power Co., and located in Satsumasendai City of Kagoshima Prefecture. The inspections are required before nuclear fuel can be loaded into the reactor.

Sendai NPPs

Now that pre-loading procedures have been completed, Kyushu Electric Power began loading the first of 157 fuel assemblies today at Sendai-1, and will continue doing so for four days or so. The reactor is expected to resume operation in mid-August, after having been shut down in May 2011, with commercial operation to begin the following month.

The NRA began the pre-service inspections at the end of March of this year to ascertain whether the equipment and facilities at the reactor were in accordance with the results of safety examinations under new regulatory standards, as well as whether they had the necessary capabilities. All of those are preconditions for restarting NPPs in Japan.

Sendai-1 will make joint use of equipment and facilities on the side closer to Sendai-2; the final inspections completed on July 3 involved those. Meanwhile, the pre-service inspections at Sendai-1 had already been completed on June 19.

Starting today, Kyushu Electric Power intends to load about 40 fuel assemblies into the reactor daily. Three days from now, on July 10, it plans to check whether the assemblies were loaded properly. Thereafter, it will run water through piping to check for leakage. It will also conduct a drill prior to the restart so as to prevent severe accidents.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)

23 January, 2020
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)07:47

Recent News

30 June, 2020
“Existing NPPs to Enter Age of 80-Year Operations” JAIF Annual Survey Says
16 June, 2020
Toshiba ESS and Yokohama National University Boost Joint Research to Upgrade Heavy-Ion Cancer Therapy, Using Kanagawa Prefectural Facility
8 June, 2020
NRA Grants Permission to Make Changes to Reactor Installation at HTTR under New Regulatory Standards
22 May, 2020
Sendai-2 Starts Periodic Inspection, with Due Date Imminent to Install Specific Safety Facilities
15 May, 2020
NRA Issues Draft Review Report for Rokkasho Reprocessing Plant
30 April, 2020
Construction Begins of Next Generation Synchrotron Radiation Facility at Tohoku University, to Be Used for Fuel Cells and Pharmaceuticals
27 April, 2020
Superconducting-Coil Tokamak Plasma Test Device (JT-60SA) Installed at Naka Fusion Institute, with Plasma Generation to Begin in Autumn
17 April, 2020
Japan’s CO2 Emissions Fall 4.6% in FY18, Thanks in Part to Restart of NPPs
14 April, 2020
ANRE Begins Hearing from Concerned Parties on Handling of Treated Contaminated Water at Fukushima Daiichi NPPs
14 April, 2020
IAEA Issues Report Reviewing Treated Contaminated Water at Fukushima Daiichi NPPs, Praising Earlier ANRE Report
▲TOP