Japanese Power Companies to Cooperate with Each Other to Complete Anti-terrorism Facilities More Quickly

On May 17, Chairman Satoru Katsuno of Japan’s Federation of Electric Power Companies (FEPC) expressed the intention of its members to hasten the construction of anti-terrorism facilities at nuclear power plants (NPPs) nationwide. To do that, they will cooperate with each other as much as possible in the procurement of equipment, among other matters.

The move was made in response to a statement by the Nuclear Regulation Authority (NRA) (refer to the Atoms in Japan article of April 24), saying that it would suspend the NPPs’ operation if such facilities—the work on which has fallen behind schedule—are not completed by the respective deadlines.

In reference to the NRA’s rejection of a request to extend the deadlines for construction of such facilities, Katsuno said at a press conference that the power companies had “insufficiently” communicated the details of their respective construction periods of the anti-terrorism facilities with the NRA, but would now endeavor to complete them “as soon as possible, to the best of their ability, to minimize the suspension periods or—if possible—avoid them altogether.”

Adding that the power companies would cooperate with each other whenever and wherever they could, Katsuno mentioned, “We haven’t discussed anything specific yet; that will be our task from now on.”

The installation of anti-terrorism facilities is required under the NRA’s new regulatory standards, with the deadline being “five years from the time that each construction plan is approved.” However, three of the utilities—namely, the Kansai Electric Power Co. (Kansai EP), the Shikoku Electric Power Co. and the Kyushu Electric Power Co.—had pointed out that they expected an additional twelve to thirty months to be needed beyond that limit for the facilities at ten of their NPPs.

On May 16, Kyushu Electric submitted the construction plan for anti-terrorism facilities for its Genkai-3 (PWR, 1180MWe). That unit has been restarted, with the deadline for completing such facilities coming in August 2022.

Although the company had said that it would be difficult to complete the construction before the deadline, it suddenly submitted a portion of the plan to the NRA, hoping to meet the deadline by successively starting work on each separate item one by one once it receives the individual approval for it.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, July 2019)

8 July, 2019
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, July 2019)09:17

Recent News

13 December, 2019
NRA Approves Decommissioning Plans for Kansai EP’s Ohi-1 and-2
12 December, 2019
JAEA Holds International Forum on Peaceful Use of Nuclear Energy, Nuclear Non-Proliferation and Nuclear Security
29 November, 2019
NRA Issues Draft Review Report: Onagawa-2 Meets New Regulatory Standards
28 November, 2019
RIKEN Unveils Transportable Compact Neutron Source System
27 November, 2019
JAIF Releases Results of Fact-Finding Survey of Japanese Nuclear Industry for Fiscal 2018
26 November, 2019
Hitachi Receives Order from Mayo Clinic to Build First Carbon Ion Treatment System in North America
25 November, 2019
Keidanren: Japan’s Commitment to Low-Carbon Society Shows NPP Restarts Helped Reduce CO2 Emissions in Fiscal 2018
21 November, 2019
TEPCO Announces Timeline for Storage and Disposal of Treated Contaminated Water at Fukushima Daiichi
15 November, 2019
JAEA Holds Public Meeting, Discusses Future Vision, Fukushima Reconstruction and Revitalization
15 November, 2019
IAEA/RCA Symposium: Cooperating with Developing Countries Through Nuclear Science and Technology
▲TOP