JAPC Applies for Permission to Bury Tokai-1 Waste on Plant Premises

On July 16, the Japan Atomic Power Co. (JAPC), under the terms of a local nuclear safety agreement, submitted a plan to Ibaraki Prefecture and Tokai Village to bury extremely low-level radioactive waste (Level III or L3) generated by the current decommissioning of its Tokai-1 Nuclear Power Plant (GCR, 166 MWe), located in the village. At the same time, JAPC also filed an application with the Nuclear Regulation Authority (NRA) for approval to bury the waste.

The waste burial is to take place on the premises of the nuclear power plant, which is the country’s first commercial reactor to be decommissioned. This is also the first time in Japan that a commercial NPP operator has submitted an application for an L3 burial plan connected with a reactor’s decommissioning.

The plan calls for the creation of a trench on the Tokai-1 premises that will be 100m long, 80m wide and 4m deep. The L3 waste will be first put in flexible container (flecon) bags and then buried in the trench, where it will remain under control for three to five decades as it becomes less radioactive. The trench will be capable of accommodating about 26,400 cubic meters of waste, with the total amount of waste to be buried expected to be some 16,000 tons.

After considering the plan, which includes both management methods and safety measures, both the prefecture and village will decide whether to give their consent, and the NRA will also determine whether to approve it or not. Once the NRA does give it the green light, JAPC will begin work on constructing the trench, targeting FY18 (April 2018 to March 2019) for the onset of operation.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)

23 January, 2020
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)07:47

Recent News

22 May, 2020
Sendai-2 Starts Periodic Inspection, with Due Date Imminent to Install Specific Safety Facilities
15 May, 2020
NRA Issues Draft Review Report for Rokkasho Reprocessing Plant
30 April, 2020
Construction Begins of Next Generation Synchrotron Radiation Facility at Tohoku University, to Be Used for Fuel Cells and Pharmaceuticals
27 April, 2020
Superconducting-Coil Tokamak Plasma Test Device (JT-60SA) Installed at Naka Fusion Institute, with Plasma Generation to Begin in Autumn
17 April, 2020
Japan’s CO2 Emissions Fall 4.6% in FY18, Thanks in Part to Restart of NPPs
14 April, 2020
ANRE Begins Hearing from Concerned Parties on Handling of Treated Contaminated Water at Fukushima Daiichi NPPs
14 April, 2020
IAEA Issues Report Reviewing Treated Contaminated Water at Fukushima Daiichi NPPs, Praising Earlier ANRE Report
3 April, 2020
Minamisoma City Releases PR Videos about Plan to Become a “Robot Innovation City”
3 April, 2020
TEPCO Presents Ten-Year Decommissioning Midterm Action Plan for Fukushima Daiichi NPS
27 March, 2020
NRA Issues Draft Review Report for JAEA’s HTTR
▲TOP