JAPC Applies for Permission to Bury Tokai-1 Waste on Plant Premises

On July 16, the Japan Atomic Power Co. (JAPC), under the terms of a local nuclear safety agreement, submitted a plan to Ibaraki Prefecture and Tokai Village to bury extremely low-level radioactive waste (Level III or L3) generated by the current decommissioning of its Tokai-1 Nuclear Power Plant (GCR, 166 MWe), located in the village. At the same time, JAPC also filed an application with the Nuclear Regulation Authority (NRA) for approval to bury the waste.

The waste burial is to take place on the premises of the nuclear power plant, which is the country’s first commercial reactor to be decommissioned. This is also the first time in Japan that a commercial NPP operator has submitted an application for an L3 burial plan connected with a reactor’s decommissioning.

The plan calls for the creation of a trench on the Tokai-1 premises that will be 100m long, 80m wide and 4m deep. The L3 waste will be first put in flexible container (flecon) bags and then buried in the trench, where it will remain under control for three to five decades as it becomes less radioactive. The trench will be capable of accommodating about 26,400 cubic meters of waste, with the total amount of waste to be buried expected to be some 16,000 tons.

After considering the plan, which includes both management methods and safety measures, both the prefecture and village will decide whether to give their consent, and the NRA will also determine whether to approve it or not. Once the NRA does give it the green light, JAPC will begin work on constructing the trench, targeting FY18 (April 2018 to March 2019) for the onset of operation.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

Grossi on Fukushima: Marking a Decade Since the Accident

10 March, 2021
Grossi on Fukushima: Marking a Decade Since the Accident04:11

Recent News

14 September, 2021
IAEA Deputy Director General Evrard Visits Japan in Advance of Safety Review of ALPS-treated Water
1 September, 2021
Evaluation Report Issued by IAEA’s Review Mission to Fukushima Daiichi: First Visit since 2018
24 August, 2021
METI and IAEA Agree on Further Review Missions to Fukushima Daiichi
4 August, 2021
JAEA Restarts High-Temperature Engineering Test Reactor “HTTR”
2 August, 2021
Information about Fukushima Daiichi NPS Water Treatment
28 July, 2021
METI’s Committee Shows Rough Draft of Next Strategic Energy Plan
2 July, 2021
Mihama-3 Restarted After Decade-long Hiatus: First Restart in Japan of a Reactor Operating Beyond 40 Years
28 June, 2021
Mihama-3 Restarts after Decade-long Hiatus
25 June, 2021
New Canada-Japan Partnership Supports Greater Collaboration to Meet Climate Change Objectives and Net-zero Goals
24 June, 2021
METI Issues New Green Growth Strategy Through Achieving Carbon Neutrality
16 June, 2021
ANRE Sticks to “S+3E”
16 June, 2021
Japanese Cabinet Approves Environmental White Paper 2021
16 June, 2021
LDP Parliamentary Association to Reconfirm Position on Utilization of Nuclear Power
16 June, 2021
Fukui Governor Concerned about Deletion of Reference to “Maximum Utilization” of Nuclear Power
14 June, 2021
Working Group on Offshore Release of Treated Water Meets in Miyagi
14 June, 2021
NRA Considers Policy on Treating Slurry from ALPS, with Local Understanding Essential
11 June, 2021
Japanese Cabinet Approves Energy White Paper 2021
11 June, 2021
Government Omits Description of “Maximum Utilization” of Nuclear Power
9 June, 2021
MNF Hopes to Resume Fuel Production as Early as November
8 June, 2021
TEPCO to Develop Sample Tanks at Fukushima Daiichi to Prepare for Offshore Release of Treated Water
▲TOP