JAPAN ATOMIC INDUSTRIAL FORUM, INC.

for Japanese

ATOMS in JAPAN

25 May, 2016

Kansai EP and JAPC Draw Up Measures for Regional Growth toward NPP Decommissioning

On May 19, the Kansai Electric Power Co. (Kansai EP) and the Japan Atomic Power Company (JAPC), presented to Fukui Prefecture and Tsuruga City work plans that they formulated for the next three years toward the decommissioning of the Mihama-1 and -2 and Tsuruga-1 Nuclear Power Plants, respectively.

JAPC's Tsuruga-1

They also presented measures for development and employment, as well as the promotion of local industries. The plans were all based on decommissioning agreements concluded in February between the companies and the two local governments.

The decommissioning plan for Kansai EP’s Mihama-1 and -2, submitted to the Nuclear Regulation Authority (NRA), requires 30 years for the entire decommissioning process. Work for the three-year period to FY18—the first half of a preparatory period before dismantling—will include system decontamination, investigations of radioactivity inside the facilities, the removal of unused fuel assemblies, and the dismantling of equipment inside the turbine buildings.

Total estimated costs are approximately JPY8 billion (USD 72.72 million at USD1=JPY110).

With the cooperation with the Wakasa Wan Energy Research Center, Kansai EP and JAPC will hold a meeting at the end of June to provide information to industries in the prefecture that may be interested in participating in the decommissioning work.

The two companies will also promote collaboration among industry, academia and the public sector in the areas of R&D and human resource development so as to strengthen the technological foundation for regional development and growth.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)

23 January, 2020
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)07:47

Recent News

7 August, 2020
Nuclear Powered Ship Mutsu Designated as Special “Ship Heritage”
3 August, 2020
On Taking Office as JAIF President
3 August, 2020
Nuclear Energy Buyers Guide in Japan 2020-21 is now available
31 July, 2020
Thoughts on the Decision to Approve Changes to the Reprocessing Business
31 July, 2020
NRA Permits JNFL to Alter Rokkasho Reprocessing Plant, Its Having Complied with New Regulatory Standards
30 June, 2020
“Existing NPPs to Enter Age of 80-Year Operations” JAIF Annual Survey Says
16 June, 2020
Toshiba ESS and Yokohama National University Boost Joint Research to Upgrade Heavy-Ion Cancer Therapy, Using Kanagawa Prefectural Facility
8 June, 2020
NRA Grants Permission to Make Changes to Reactor Installation at HTTR under New Regulatory Standards
22 May, 2020
Sendai-2 Starts Periodic Inspection, with Due Date Imminent to Install Specific Safety Facilities
15 May, 2020
NRA Issues Draft Review Report for Rokkasho Reprocessing Plant
▲TOP