On March 14, the Kansai Electric Power Co. (Kansai EP) of Japan filed an objection with the Otsu District Court against the temporary injunction that the court had issued on March 9, which halted operation of the Units 3 and 4 of the Takahama Nuclear Power Plants (both PWRs, 870MWe each) in Takahama Town, Fukui Prefecture.

Takahama-3&4

As of now, however, the temporary injunction remains in effect. Unless judicial relief is granted to Kansai EP, the power company will not be able to resume operation of the two units. The court’s examination and consideration of the company’s latest filing is expected to take at least several months.

Following the court’s order on March 9, Kansai EP stopped operating Unit 3 on March 10. Takahama-4 was already shut down owing to a problem that had occurred immediately after being restarted in February.

The decision by the Otsu District Court pointed to problems in both reactors regarding such matters as design concepts, earthquake resistance, tsunami measures, and evacuation plans, based on the experience of the March 2011 accident at the Fukushima Daiichi Nuclear Power Plants. “There is keen fear that the personal rights of residents are being violated, and that Kansai EP has not sufficiently explained that safety is secured,” the court said.

Safety of the reactors’ operations has, of course, already been approved by the nuclear regulator, namely, the Nuclear Regulation Authority (NRA). However, nuclear operators in Japan now find themselves in the position of having to obtain the approval of judicial entities as well. Attention is thus now also on how the NRA—the regulatory authority that had already approved the reactors’ safety—will react.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

Grossi on Fukushima: Marking a Decade Since the Accident

10 March, 2021
Grossi on Fukushima: Marking a Decade Since the Accident04:11

Recent News

28 July, 2021
METI’s Committee Shows Rough Draft of Next Strategic Energy Plan
2 July, 2021
Mihama-3 Restarted After Decade-long Hiatus: First Restart in Japan of a Reactor Operating Beyond 40 Years
28 June, 2021
Mihama-3 Restarts after Decade-long Hiatus
25 June, 2021
New Canada-Japan Partnership Supports Greater Collaboration to Meet Climate Change Objectives and Net-zero Goals
24 June, 2021
METI Issues New Green Growth Strategy Through Achieving Carbon Neutrality
16 June, 2021
ANRE Sticks to “S+3E”
16 June, 2021
Japanese Cabinet Approves Environmental White Paper 2021
16 June, 2021
LDP Parliamentary Association to Reconfirm Position on Utilization of Nuclear Power
16 June, 2021
Fukui Governor Concerned about Deletion of Reference to “Maximum Utilization” of Nuclear Power
14 June, 2021
Working Group on Offshore Release of Treated Water Meets in Miyagi
14 June, 2021
NRA Considers Policy on Treating Slurry from ALPS, with Local Understanding Essential
11 June, 2021
Japanese Cabinet Approves Energy White Paper 2021
11 June, 2021
Government Omits Description of “Maximum Utilization” of Nuclear Power
9 June, 2021
MNF Hopes to Resume Fuel Production as Early as November
8 June, 2021
TEPCO to Develop Sample Tanks at Fukushima Daiichi to Prepare for Offshore Release of Treated Water
8 June, 2021
Opinions Differ Within Japan’s Governing Coalition Concerning Nuclear Power
8 June, 2021
Local Concerns About Unfounded Fears and Rumors on Offshore Release of Treated Water
7 June, 2021
JEMA Proposes that Nuclear Power Be Maintained at a Certain Scale
7 June, 2021
IHI to Participate in NuScale’s SMR Project
4 June, 2021
FEPC Declares for “Zero Emissions”
▲TOP