18 May, 2021

Kansai EP Reveals Policy on NPPs Set to Operate Beyond 40 Years, with Mihama-3 to Restart in Late June

On May 12, the Kansai Electric Power Co. (Kansai EP) announced its plans regarding the restart of its Mihama-3 (PWR, 826MWe) and Takahama-1 and -2 (PWRs, 826MWe each) Nuclear Power Plants (NPPs).

Unit 3 is on the right

In 2016, based on examinations by the Nuclear Regulation Authority of Japan (NRA) to confirm the compatibility of the three units with the new regulatory standards, the power utility was granted approval to make changes to the reactor installations (basic design approval) and to extend their operating lifetimes to sixty years.

Kansai EP has been carrying out activities to implement safety and disaster measures and to obtain local understanding. On April 28, the governor of Fukui Prefecture expressed his agreement to restarting the reactors.

At the Mihama-3, fuel will start being loaded on May 20, and the reactor will be restarted and will resume generation in late June. The following month, after a period of adjustment operations, Mihama-3 is expected to return to full service after a decade. It will be the first NPP in Japan to operate beyond forty years.

Thereafter, however, the operation of Mihama-3 will be suspended again before the expected restart, since the facilities have not been completed for responding to specific severe accidents—termed “specific safety facilities”—which are required under the new regulatory standards as anti-terrorism measures. The deadline for completing those facilities is October 25, and their design and (initial) work plans were only approved by the NRA in April.

Fuel began to be loaded at the Takahama-1 on May 14. During the loading, Kansai EP will conduct related inspections to confirm the soundness of facilities and equipment. The Takahama-2, meanwhile, is now undergoing work on safety improvement measures.

However, since the deadlines for the “specific safety facilities” are imminent for both units (namely, June 9), no times have been shown for their restart. They will only be restarted once the required work is completed.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

Grossi on Fukushima: Marking a Decade Since the Accident

10 March, 2021
Grossi on Fukushima: Marking a Decade Since the Accident04:11

Recent News

16 June, 2021
ANRE Sticks to “S+3E”
16 June, 2021
Japanese Cabinet Approves Environmental White Paper 2021
16 June, 2021
LDP Parliamentary Association to Reconfirm Position on Utilization of Nuclear Power
16 June, 2021
Fukui Governor Concerned about Deletion of Reference to “Maximum Utilization” of Nuclear Power
14 June, 2021
Working Group on Offshore Release of Treated Water Meets in Miyagi
14 June, 2021
NRA Considers Policy on Treating Slurry from ALPS, with Local Understanding Essential
11 June, 2021
Japanese Cabinet Approves Energy White Paper 2021
11 June, 2021
Government Omits Description of “Maximum Utilization” of Nuclear Power
9 June, 2021
MNF Hopes to Resume Fuel Production as Early as November
8 June, 2021
TEPCO to Develop Sample Tanks at Fukushima Daiichi to Prepare for Offshore Release of Treated Water
8 June, 2021
Opinions Differ Within Japan’s Governing Coalition Concerning Nuclear Power
8 June, 2021
Local Concerns About Unfounded Fears and Rumors on Offshore Release of Treated Water
7 June, 2021
JEMA Proposes that Nuclear Power Be Maintained at a Certain Scale
7 June, 2021
IHI to Participate in NuScale’s SMR Project
4 June, 2021
FEPC Declares for “Zero Emissions”
4 June, 2021
Support Grows Within LDP for Nuclear Power
2 June, 2021
JAIF Reports to JAEC on JAIF Annual Conference
2 June, 2021
Japan’s Power Industry Workers Union Calls for Prudence toward the Closure of Coal-fired Power Plants
2 June, 2021
Japan’s Advisory Committee Discusses Supply-and-Demand Measures in Summer and Winter 2021
1 June, 2021
Preparations Continue Toward Restarting Tokai-2 NPP
▲TOP