10 September, 2019

Kyushu Electric Power Files Decommissioning Plan for Genkai-2 and Seeks Change to Genkai-1 Plan, with Work on Both to Proceed Simultaneously

On September 3, the Kyushu Electric Power Co. filed an application with the Nuclear Regulation Authority (NRA) of Japan for approval of its plan to decommission its Genkai-2 Nuclear Power Plant (PWR, 559MWe). The power company also requested preliminary talks with Saga Prefecture and Genkai Town under nuclear safety agreements with each of them.

Genkai NPPs

While making the application for Genkai-2, Kyushu Electric Power also asked the NRA to approve a change to its decommissioning plan for Genkai-1, the work on which is already underway. It seeks to revise its processes in that way to take advantage of the benefits accrued from carrying out work on the two units at the same time.

However, that move will push back the completion date for Unit 1 eleven years, with the decommissioning work on both units now slated to end in 2054.

The entire decommissioning process for Genkai-2 is divided into four stages, as follows:

  1. Preparing for dismantling.
  2. Dismantling and removing facilities and equipment in the area surrounding the reactor.
  3. Dismantling and removing the reactor itself.
  4. Dismantling and removing the reactor building and other structures.

The removal of spent fuel assemblies from Unit 2 facilities will be completed during the second stage above, which is expected to last from 2026 to 2040. The spent fuel thus removed will be transferred to a licensee for reprocessing activities by the time the decommissioning is completed.

Because the available workspace during the second stage will be halved, given that the decommissioning work on both reactors will be carried out simultaneously, Kyushu Electric Power has calculated that the stage will take twice as long as originally expected. After that, the start and end of each subsequent stage will be the same for both units. Meanwhile, work at Unit 1 needs to be slowed down in order to let that at Unit 2 catch up, necessitating a delay of eleven years beyond what was initially planned.

At present, twenty-four reactor units in Japan are either being decommissioned or have been designated for that work (including Fukushima Daiichi 1 to 6). With decommissioning thus getting into full swing, the Japan Atomic Power Company (JAPC) reported on the current status of the work at a meeting of the Japan Atomic Energy Commission (JAEC) on September 3, along with various issues.

Toyoaki Yamauchi, senior executive officer and general manager of the Decommissioning Project Department of JAPC, pointed to several elements as necessary for safe, efficient decommissioning, as follows:

  • Having a decommissioning culture and mindset.
  • Securing destinations to which waste from dismantling will be taken.
  • Getting decommissioning funds and developing an accounting system.
  • Carrying out the appropriate regulation of the decommissioning.

Yamauchi also introduced the Earned Value Management System (EVMS) being applied by JAPC together with EnergySolutions, a firm in the United States specializing in decommissioning. In so doing, he emphasized the importance of project management for successful decommissioning.

Also on September 3, representatives of the Chubu Electric Power Co., in an exchange of opinions with the NRA, explained its ongoing dismantling work at the Hamaoka-1 and -2 NPPs. The power company said that an estimated 80,000 tons (17 percent) or so of the approximately 450,000 tons of combined waste from dismantling both units could be subject to clearance.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, July 2019)

8 July, 2019
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, July 2019)09:17

Recent News

23 January, 2020
Finishing Mission in Japan, IAEA’s IRRS Points Out Importance of NRA’s Communicating with Nuclear Industry
21 January, 2020
Evacuation Orders for Futaba, Okuma, Tomioka Towns to Be Partially Lifted in March, with JR Joban Line to Be Completely Reopened for Service
16 January, 2020
Japan’s Nuclear Power Plant Capacity Factor Stood at Just 21.4 Percent Last Year
26 December, 2019
IEEJ’s Supply-Demand Outlook for FY2020 Looks at Effect of Specific Safety Facility Installation Deadlines
25 December, 2019
ANRE Committee Clarifies Options for Treated Contaminated Water at Fukushima Daiichi NPPs, Viewing Both Offshore and Vapor Release Favorably
24 December, 2019
Fuel Removal from Fukushima Daiichi-1 NPP: Large Cover to be Installed First
18 December, 2019
JAEC Begins Hearing from University Personnel on Human Resource Development, Starting with Nagoya and Osaka Universities
13 December, 2019
NRA Approves Decommissioning Plans for Kansai EP’s Ohi-1 and-2
12 December, 2019
JAEA Holds International Forum on Peaceful Use of Nuclear Energy, Nuclear Non-Proliferation and Nuclear Security
29 November, 2019
NRA Issues Draft Review Report: Onagawa-2 Meets New Regulatory Standards
▲TOP