28 December, 2015

Kyushu Electric Power Submits Application for Genkai-1 Decommissioning Plan

On December 22, Japan's Kyushu Electric Power Co. submitted an application to the Nuclear Regulation Authority (NRA) for approval of a decommissioning plan for Unit 1 of the Genkai Nuclear Power Plant (PWR, 559MWe), located in Genkai Town in Saga Prefecture on the island of Kyushu.

Genkai-1 (center)

Among the five aging NPPs closed nationwide in April 2015, this is the first for which a decommissioning plan has actually been submitted. Seeking to start work in FY16, Kyushu Electric intends to complete the decommissioning over the next 28 years, by FY43 (starting April 2043).

According to the plan, the decommissioning process, to take place over the 28-year period from FY16 to FY43, will be roughly divided into four phases, as follows:

  • Preparing for the dismantling work (FY16-21)
  •  Dismantling and removing the facilities and other equipment surrounding the reactor (FY22-29)
  •  Dismantling and removing the reactor, etc. (FY30-36)
  •  Dismantling the reactor building, etc. (FY37-43)

During the preparation phase, Kyushu Electric, at the same time as it dismantles and removes the non-contaminated equipment, will investigate how much radioactive contamination there is, and carry out decontamination work.

During the next phase of dismantling and removing the equipment surrounding the reactor, the power company will then remove spent the nuclear fuel from the reactor building and transfer it to the spent fuel reprocessing licensee.

The total volume of contaminated waste is expected to be as much as 7,020 tons, which will be delivered to the waste disposal licensees according to the levels and properties of the radioactivity. Materials not requiring handling as radioactive waste will be recycled as much as possible.

In addition to Genkai-1, four other aging NPPs all ceased operations officially at the end of April 2015: Tsuruga-1, owned and operated by the Japan Atomic Power Company (JAPC), Mihama-1 and -2, owned and operated by the Kansai Electric Power Co. (Kansai EP), and Shimane-1, owned and operated by the Chugoku Electric Power Co.

The NRA is currently working on regulatory standards for radioactive waste, including reactor core internals.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, July 2019)

8 July, 2019
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, July 2019)09:17

Recent News

16 January, 2020
Japan’s Nuclear Power Plant Capacity Factor Stood at Just 21.4 Percent Last Year
26 December, 2019
IEEJ’s Supply-Demand Outlook for FY2020 Looks at Effect of Specific Safety Facility Installation Deadlines
25 December, 2019
ANRE Committee Clarifies Options for Treated Contaminated Water at Fukushima Daiichi NPPs, Viewing Both Offshore and Vapor Release Favorably
24 December, 2019
Fuel Removal from Fukushima Daiichi-1 NPP: Large Cover to be Installed First
18 December, 2019
JAEC Begins Hearing from University Personnel on Human Resource Development, Starting with Nagoya and Osaka Universities
13 December, 2019
NRA Approves Decommissioning Plans for Kansai EP’s Ohi-1 and-2
12 December, 2019
JAEA Holds International Forum on Peaceful Use of Nuclear Energy, Nuclear Non-Proliferation and Nuclear Security
29 November, 2019
NRA Issues Draft Review Report: Onagawa-2 Meets New Regulatory Standards
28 November, 2019
RIKEN Unveils Transportable Compact Neutron Source System
27 November, 2019
JAIF Releases Results of Fact-Finding Survey of Japanese Nuclear Industry for Fiscal 2018
▲TOP