Kyushu Electric Power Submits Application for Genkai-1 Decommissioning Plan

On December 22, Japan's Kyushu Electric Power Co. submitted an application to the Nuclear Regulation Authority (NRA) for approval of a decommissioning plan for Unit 1 of the Genkai Nuclear Power Plant (PWR, 559MWe), located in Genkai Town in Saga Prefecture on the island of Kyushu.

Genkai-1 (center)

Among the five aging NPPs closed nationwide in April 2015, this is the first for which a decommissioning plan has actually been submitted. Seeking to start work in FY16, Kyushu Electric intends to complete the decommissioning over the next 28 years, by FY43 (starting April 2043).

According to the plan, the decommissioning process, to take place over the 28-year period from FY16 to FY43, will be roughly divided into four phases, as follows:

  • Preparing for the dismantling work (FY16-21)
  •  Dismantling and removing the facilities and other equipment surrounding the reactor (FY22-29)
  •  Dismantling and removing the reactor, etc. (FY30-36)
  •  Dismantling the reactor building, etc. (FY37-43)

During the preparation phase, Kyushu Electric, at the same time as it dismantles and removes the non-contaminated equipment, will investigate how much radioactive contamination there is, and carry out decontamination work.

During the next phase of dismantling and removing the equipment surrounding the reactor, the power company will then remove spent the nuclear fuel from the reactor building and transfer it to the spent fuel reprocessing licensee.

The total volume of contaminated waste is expected to be as much as 7,020 tons, which will be delivered to the waste disposal licensees according to the levels and properties of the radioactivity. Materials not requiring handling as radioactive waste will be recycled as much as possible.

In addition to Genkai-1, four other aging NPPs all ceased operations officially at the end of April 2015: Tsuruga-1, owned and operated by the Japan Atomic Power Company (JAPC), Mihama-1 and -2, owned and operated by the Kansai Electric Power Co. (Kansai EP), and Shimane-1, owned and operated by the Chugoku Electric Power Co.

The NRA is currently working on regulatory standards for radioactive waste, including reactor core internals.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

Grossi on Fukushima: Marking a Decade Since the Accident

10 March, 2021
Grossi on Fukushima: Marking a Decade Since the Accident04:11

Recent News

21 October, 2021
Kishida Makes First Visit to Fukushima Since Becoming Prime Minister
15 October, 2021
LDP Adds SMR Development and Nuclear Fusion to NPP Restarts in Its Policy Manifesto
7 October, 2021
Kishida Administration Inaugurated, with New METI Minister Hagiuda Holding Press Conference on Taking Office
6 October, 2021
IAEA Holds 65th General Conference in Vienna, with Japanese Minister of State for Science and Technology Delivering Statement in the General Debate
30 September, 2021
JAEC Releases 2020 White Paper on Nuclear Energy
17 September, 2021
NRA Permits Shimane-2 under New Regulatory Standards
14 September, 2021
IAEA Deputy Director General Evrard Visits Japan in Advance of Safety Review of ALPS-treated Water
1 September, 2021
Evaluation Report Issued by IAEA’s Review Mission to Fukushima Daiichi: First Visit since 2018
24 August, 2021
METI and IAEA Agree on Further Review Missions to Fukushima Daiichi
4 August, 2021
JAEA Restarts High-Temperature Engineering Test Reactor “HTTR”
2 August, 2021
Information about Fukushima Daiichi NPS Water Treatment
28 July, 2021
METI’s Committee Shows Rough Draft of Next Strategic Energy Plan
2 July, 2021
Mihama-3 Restarted After Decade-long Hiatus: First Restart in Japan of a Reactor Operating Beyond 40 Years
28 June, 2021
Mihama-3 Restarts after Decade-long Hiatus
25 June, 2021
New Canada-Japan Partnership Supports Greater Collaboration to Meet Climate Change Objectives and Net-zero Goals
24 June, 2021
METI Issues New Green Growth Strategy Through Achieving Carbon Neutrality
16 June, 2021
ANRE Sticks to “S+3E”
16 June, 2021
Japanese Cabinet Approves Environmental White Paper 2021
16 June, 2021
LDP Parliamentary Association to Reconfirm Position on Utilization of Nuclear Power
16 June, 2021
Fukui Governor Concerned about Deletion of Reference to “Maximum Utilization” of Nuclear Power
▲TOP