16 November, 2020

Kyushu Electric Power Starts Operating Facilities at Sendai-1 NPP Designed for “Specific Severe Accident” Response—First Time in Japan

On November 11, the Kyushu Electric Power Co. began operating facilities at its Sendai-1 Nuclear Power Plant (NPP) for responding to specific severe accidents. The term refers to safety facilities, specifically those for anti-terrorism measures. The plant is expected to resume power generation on November 26.

After approval is given for a work plan for the main body of a plant, a five-year grace period is granted for the installation of the “specific safety facilities” required by the new regulatory standards. Nationwide, the Sendai-1 was the first to restart, in 2015. Specific safety facilities there are also the first to be operated.

Sendai-1 entered a periodic inspection one day prior to the deadline of March 17 for the installation of the facilities at the unit. Initially, its operation had been scheduled to resume on December 26 of this year, but it will start one month earlier thanks to the faster than expected work on the specific safety facilities.

The Sendai-2 similarly entered a periodic inspection on May 20 of this year, and is also scheduled to resume operation on December 26, once its specific safety facilities are completely installed.

Although details of specific safety facilities are not disclosed for security reasons, they include the installation and positioning of emergency control rooms, power sources, water-injection pumps, etc. away from the reactor buildings, with the aim of preventing damage to the reactor containment vessels if major damage occurs.

Elsewhere, deadlines passed in October for the installation of specific safety facilities at the Takahama-3 and -4, owned and operated by the Kansai Electric Power Co. (Kansai EP), and both are now undergoing periodic inspections.

On October 7, the Nuclear Regulation Authority (NRA) gave approvals for their specific safety facilities of revisions to operational safety programs, including training items. Takahama-3 and -4 are expected to be back online, respectively, in mid-January and mid-February 2021.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

Grossi on Fukushima: Marking a Decade Since the Accident

10 March, 2021
Grossi on Fukushima: Marking a Decade Since the Accident04:11

Recent News

21 October, 2021
Kishida Makes First Visit to Fukushima Since Becoming Prime Minister
15 October, 2021
LDP Adds SMR Development and Nuclear Fusion to NPP Restarts in Its Policy Manifesto
7 October, 2021
Kishida Administration Inaugurated, with New METI Minister Hagiuda Holding Press Conference on Taking Office
6 October, 2021
IAEA Holds 65th General Conference in Vienna, with Japanese Minister of State for Science and Technology Delivering Statement in the General Debate
30 September, 2021
JAEC Releases 2020 White Paper on Nuclear Energy
17 September, 2021
NRA Permits Shimane-2 under New Regulatory Standards
14 September, 2021
IAEA Deputy Director General Evrard Visits Japan in Advance of Safety Review of ALPS-treated Water
1 September, 2021
Evaluation Report Issued by IAEA’s Review Mission to Fukushima Daiichi: First Visit since 2018
24 August, 2021
METI and IAEA Agree on Further Review Missions to Fukushima Daiichi
4 August, 2021
JAEA Restarts High-Temperature Engineering Test Reactor “HTTR”
2 August, 2021
Information about Fukushima Daiichi NPS Water Treatment
28 July, 2021
METI’s Committee Shows Rough Draft of Next Strategic Energy Plan
2 July, 2021
Mihama-3 Restarted After Decade-long Hiatus: First Restart in Japan of a Reactor Operating Beyond 40 Years
28 June, 2021
Mihama-3 Restarts after Decade-long Hiatus
25 June, 2021
New Canada-Japan Partnership Supports Greater Collaboration to Meet Climate Change Objectives and Net-zero Goals
24 June, 2021
METI Issues New Green Growth Strategy Through Achieving Carbon Neutrality
16 June, 2021
ANRE Sticks to “S+3E”
16 June, 2021
Japanese Cabinet Approves Environmental White Paper 2021
16 June, 2021
LDP Parliamentary Association to Reconfirm Position on Utilization of Nuclear Power
16 June, 2021
Fukui Governor Concerned about Deletion of Reference to “Maximum Utilization” of Nuclear Power
▲TOP