21 October, 2016

METI Proposes Revising Accounting Method to Shorten Deposit Period for Dismantling Costs by Ten Years

On October 19, Japan's Ministry of Economy, Trade and Industry (METI) held a meeting of its task force on decommissioning accounting, under the subcommittee on measures to carry through with electricity system reform. The meeting produced a proposal to shorten the deposit period for costs for dismantling nuclear reactors from fifty to forty years.

Currently, the period includes the decade after reactors stop operating. With the change, the total amount will be accumulated during operations, thereby ensuring funds, even as the country’s retail power market continues to be deregulated further, and even after all related regulations are abolished.

Under the present system, each Japanese power utility with nuclear power plants (NPPs) must estimate its total costs for reactor dismantling and the disposal of radioactive waste in advance, collecting the appropriate amounts from within power rates over a period of fifty years (specifically, forty years of operation plus ten years afterward).

In 2020, however, Japan will abolish all power rate regulation in the electricity market, including the adding of costs for decommissioning, with a full shift to a free-rate system. Power utilities will thus have to fund decommissioning from their own profits. It is expected that it will be difficult for them to continue to set aside money after reactors cease operation.

According to the proposal, a review can be made of the deposit period if operating lifetimes are extended, with total estimates changed depending on individual circumstances.

Meanwhile, the matter of decommissioning accounting for the Fukushima Daiichi NPPs, owned by the Tokyo Electric Power Co. (TEPCO), will also be addressed, based on deliberations by a separate expert panel.

If a power utility decides to decommission a unit earlier than expected, the costs can be posted in installments, following a system introduced in 2013.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

Voices from Nuclear Industry – Contributing to a clean and resilient recovery

3 September, 2020
Voices from Nuclear Industry – Contributing to a clean and resilient recovery03:59

Recent News

23 September, 2020
Hitachi to End Business Operations on UK Nuclear Power Project
15 September, 2020
Japan’s Cabinet Office to Hold Virtual Side Event on Radiation Cancer Therapy at IAEA General Conference
10 September, 2020
New Report Released on Nuclear Power’s Role in Dealing with Environment Issues
4 September, 2020
Japan’s NRA Says RFS’s Recyclable-Fuel Storage Center Is Compatible with Regulatory Standards
3 September, 2020
JAIF Issues Joint Video Message with Foreign Counterparts
27 August, 2020
METI Minister Kajiyama Stresses Importance of Realizing HLW Final Disposal
7 August, 2020
Nuclear Powered Ship Mutsu Designated as Special “Ship Heritage”
3 August, 2020
On Taking Office as JAIF President
3 August, 2020
Nuclear Energy Buyers Guide in Japan 2020-21 is now available
31 July, 2020
Thoughts on the Decision to Approve Changes to the Reprocessing Business
▲TOP