2 July, 2021

Mihama-3 Restarted After Decade-long Hiatus: First Restart in Japan of a Reactor Operating Beyond 40 Years

On June 29, the Mihama-3 Nuclear Power Plant (PWR, 826MW) of the Kansai Electric Power Co. (Kansai EP) began to again generate power after a hiatus of slightly more than 10 years.

Unit 3 is on the right

Mihama-3 originally began commercial operation in December 1976. In May 2011, the unit entered a periodic inspection, when it underwent examinations by the Nuclear Regulation Authority (NRA) for compatibility with the new regulatory standards and for permission to extend its operating lifetime to up to 60 years.

The unit was restarted on June 23, 2021, becoming the first in Japan to be restarted after operating for more than 40 years. A period of adjustment operations is now underway before the final stage of the periodic inspection, i.e., connection to the grid. After a final inspection by the NRA, Mihama-3 is expected to resume commercial service on July 27.

In addition to work on safety measures based on the accident at the Fukushima Daiichi, Kansai EP carried out other kinds of work during the periodic inspection, including the replacement of the central control panel with the newest digital type,

However, given that required anti-terrorism facilities have not been completed, Kansai EP will halt the unit’s operation on October 23—before the deadline of October 25—after which Mihama-3 will enter yet another periodic inspection.

Upon the restart of Mihama-3, Kansai EP President Takashi Morimoto released a comment, saying, “At Mihama—the birthplace of our NPPs—we have taken another step forward, namely, operating a unit beyond 40 years. It is the first in Japan since the new regulatory standards became effective.”

Expressing again his gratitude to the siting municipalities, he said, “Each and every employee of our company, as well as of our partner companies, will carry out their work prudently, with firm determination to perpetually improve nuclear safety.”

At a meeting on June 30 of the Strategic Policy Committee, under the Advisory Committee for Natural Resources and Energy, Governor Tatsuji Sugimoto of Fukui Prefecture emphasized that utilization of all NPPs that can be restarted is essential.

The governor then expressed concern that, despite operation beyond 40 years, eventual shutdowns would affect regional development, so he asked the national government to “make its policy clear on the utilization of nuclear power in the next Strategic Energy Plan.”

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

Grossi on Fukushima: Marking a Decade Since the Accident

10 March, 2021
Grossi on Fukushima: Marking a Decade Since the Accident04:11

Recent News

13 January, 2022
METI Minister Hagiuda Discusses U.S. Nuclear Cooperation, Winter Electricity Supply and Demand
27 December, 2021
TEPCO Submits Application to NRA for Facilities to Deal with ALPS-Treated Water at Fukushima Daiichi
18 November, 2021
METI Minister Speaks to IAEA International Conference on Decade of Progress Since Fukushima Daiichi Accident
15 November, 2021
Nuclear Energy’s Contribution to Achieving SDGs
8 November, 2021
COP26: Prime Minister Kishida Announces Additional Contribution of USD10 Billion for Climate Change Measures
30 October, 2021
Reelection of Suttsu Mayor Means Literature Investigation for HLW Disposal Will Continue
21 October, 2021
Kishida Makes First Visit to Fukushima Since Becoming Prime Minister
15 October, 2021
LDP Adds SMR Development and Nuclear Fusion to NPP Restarts in Its Policy Manifesto
7 October, 2021
Kishida Administration Inaugurated, with New METI Minister Hagiuda Holding Press Conference on Taking Office
6 October, 2021
IAEA Holds 65th General Conference in Vienna, with Japanese Minister of State for Science and Technology Delivering Statement in the General Debate
30 September, 2021
JAEC Releases 2020 White Paper on Nuclear Energy
17 September, 2021
NRA Permits Shimane-2 under New Regulatory Standards
14 September, 2021
IAEA Deputy Director General Evrard Visits Japan in Advance of Safety Review of ALPS-treated Water
1 September, 2021
Evaluation Report Issued by IAEA’s Review Mission to Fukushima Daiichi: First Visit since 2018
24 August, 2021
METI and IAEA Agree on Further Review Missions to Fukushima Daiichi
4 August, 2021
JAEA Restarts High-Temperature Engineering Test Reactor “HTTR”
2 August, 2021
Information about Fukushima Daiichi NPS Water Treatment
28 July, 2021
METI’s Committee Shows Rough Draft of Next Strategic Energy Plan
2 July, 2021
Mihama-3 Restarted After Decade-long Hiatus: First Restart in Japan of a Reactor Operating Beyond 40 Years
28 June, 2021
Mihama-3 Restarts after Decade-long Hiatus
▲TOP