JAPAN ATOMIC INDUSTRIAL FORUM, INC.

for Japanese

Fukushima Daiichi-2

Current StatusUnder decommissioning

BWR  784MWe (gross)
          760MWe (net)

Owner:  

Operator:

Date of order:
1968
Construction Start:
1969-01
Concrete placing:
1969-06-09
Initial Criticality:
1973-05-10
Grid connection:
1973-12-24
Commercial Operation:
1974-07-18
Closed down:
2012-04-19
Main contractor:
GE/Toshiba
Architect Engineer:
EBASCO
Reactor System supplier:
GE/Toshiba
Reactor Vessel supplier:
GE/GETSCO/Toshiba/IHI
Incore Structure supplier:
GE/Toshiba
Fuel supplier:
NFI
Steam raising supplier:
GE/Toshiba/GETSCO
Turbine generator supplier:
GE/Toshiba/GETSCO
Civil works:
Kajima/Kumagai
SNS facebooktwitter

Video

Fukushima Daiichi Nuclear Power Station -The year in review- (March 2018 – February 2019)

8 March, 2019
Fukushima Daiichi Nuclear Power Station -The year in review- (March 2018 – February 2019)04:56

Recent News

21 May, 2019
【52nd JAIF Annual Conference】 Environmental Activist Michael Shellenberger, a Pro-nuclear Convert, Meets the Press
21 May, 2019
【52nd JAIF Annual Conference】 Leader Perspective: “The Role of Nuclear Energy in the EU Low-carbon Future”
20 May, 2019
【52nd JAIF Annual Conference】 Leader Perspective: “French Nuclear Policy and Industry Update”
20 May, 2019
【52nd JAIF Annual Conference】 Session 3: “Diversity and Possibilities for Nuclear Technology”
15 May, 2019
【52nd JAIF Annual Conference】 Session 2: “Prospects for Development of Innovative Technology”
15 May, 2019
【52nd JAIF Annual Conference】 Fukushima Daiichi Report
15 May, 2019
【52nd JAIF Annual Conference】 Session 1: “Role of Nuclear Power as a Low-Carbon Energy Source”
10 May, 2019
JT60-SA’s Core Central Solenoid Installed at QST’s Naka Fusion Institute
10 May, 2019
President of Decommissioning Company Says “Feel” from Unit 3 Will Aid Decommissioning of Other Units
10 May, 2019
Demonstration Made by MHI and IRID of Robot Arm to Remove Fuel Debris from Fukushima Daiichi
▲TOP