Genkai-2

Current StatusPermanent shutdown

PWR  559MWe (gross)
          529MWe (net)

Owner:  

Operator:

Date of order:
1976
Construction Start:
1976-06
Concrete placing:
1977-02
Initial Criticality:
1980-05-21
Grid connection:
1980-06-03
Commercial Operation:
1981-03-30
Closed down:
2019-02-13
Main contractor:
MHI
Architect Engineer:
MAPI
Reactor System supplier:
MHI
Reactor Vessel supplier:
MHI
Incore Structure supplier:
MHI
Fuel supplier:
MNF/NFI
Steam raising supplier:
MHI
Turbine generator supplier:
MHI
Civil works:
various
SNS facebooktwitter

Video

Fukushima Daiichi Nuclear Power Station -The year in review- (March 2018 – February 2019)

8 March, 2019
Fukushima Daiichi Nuclear Power Station -The year in review- (March 2018 – February 2019)04:56

Recent News

21 May, 2019
【52nd JAIF Annual Conference】 Environmental Activist Michael Shellenberger, a Pro-nuclear Convert, Meets the Press
21 May, 2019
【52nd JAIF Annual Conference】 Leader Perspective: “The Role of Nuclear Energy in the EU Low-carbon Future”
20 May, 2019
【52nd JAIF Annual Conference】 Leader Perspective: “French Nuclear Policy and Industry Update”
20 May, 2019
【52nd JAIF Annual Conference】 Session 3: “Diversity and Possibilities for Nuclear Technology”
15 May, 2019
【52nd JAIF Annual Conference】 Session 2: “Prospects for Development of Innovative Technology”
15 May, 2019
【52nd JAIF Annual Conference】 Fukushima Daiichi Report
15 May, 2019
【52nd JAIF Annual Conference】 Session 1: “Role of Nuclear Power as a Low-Carbon Energy Source”
10 May, 2019
JT60-SA’s Core Central Solenoid Installed at QST’s Naka Fusion Institute
10 May, 2019
President of Decommissioning Company Says “Feel” from Unit 3 Will Aid Decommissioning of Other Units
10 May, 2019
Demonstration Made by MHI and IRID of Robot Arm to Remove Fuel Debris from Fukushima Daiichi
▲TOP