Genkai-3

Current Statusin Operation
Applications for Restart2013-07-12
NRA's Approval for basic design2017-01-18
NRA's Approval for detailed design2017-08-25
NRA's Approval for safety program2017-09-14
Start of NRA Pre-service Inspection2017-09-11
Local Consent2017-04-24
Restart2018-05-16
Age:25

PWR  1180MWe (gross)
          1127MWe (net)

Owner:  

Operator:

Date of order:
1985
Construction Start:
1985-08
Concrete placing:
1988-06
Initial Criticality:
1993-05-28
Grid connection:
1993-06-15
Commercial Operation:
1994-03-18
Main contractor:
MHI
Architect Engineer:
MAPI
Reactor System supplier:
MHI
Reactor Vessel supplier:
MHI
Incore Structure supplier:
MHI
Fuel supplier:
MNF/NFI
Steam raising supplier:
MHI
Turbine generator supplier:
MHI
Civil works:
various
2013-07-08 2013-07-12   2017-01-18 2017-04-24 2018-05-16

New Regulatory Standards came into effect

Applications by Operator

Application for Permission to Install a Reactor
(Basic design)

NRA Approval

Local Consent
(not a legal requirement)

Restart the reactor

  2017-08-25 2017-09-11
Application for Approval of Construction Plan
(Detailed design based on basic design)

NRA Approval

Pre-service Inspection by NRA

Application for Approval of Operational Safety Program
(Matters regarding operations, including operational safety)

NRA Approval

            2017-09-14  
SNS facebooktwitter

Video

Fukushima Daiichi Nuclear Power Station -The year in review- (March 2018 – February 2019)

8 March, 2019
Fukushima Daiichi Nuclear Power Station -The year in review- (March 2018 – February 2019)04:56

Recent News

21 May, 2019
【52nd JAIF Annual Conference】 Environmental Activist Michael Shellenberger, a Pro-nuclear Convert, Meets the Press
21 May, 2019
【52nd JAIF Annual Conference】 Leader Perspective: “The Role of Nuclear Energy in the EU Low-carbon Future”
20 May, 2019
【52nd JAIF Annual Conference】 Leader Perspective: “French Nuclear Policy and Industry Update”
20 May, 2019
【52nd JAIF Annual Conference】 Session 3: “Diversity and Possibilities for Nuclear Technology”
15 May, 2019
【52nd JAIF Annual Conference】 Session 2: “Prospects for Development of Innovative Technology”
15 May, 2019
【52nd JAIF Annual Conference】 Fukushima Daiichi Report
15 May, 2019
【52nd JAIF Annual Conference】 Session 1: “Role of Nuclear Power as a Low-Carbon Energy Source”
10 May, 2019
JT60-SA’s Core Central Solenoid Installed at QST’s Naka Fusion Institute
10 May, 2019
President of Decommissioning Company Says “Feel” from Unit 3 Will Aid Decommissioning of Other Units
10 May, 2019
Demonstration Made by MHI and IRID of Robot Arm to Remove Fuel Debris from Fukushima Daiichi
▲TOP