JAPAN ATOMIC INDUSTRIAL FORUM, INC.

for Japanese

Ikata-3

Current Statusin Operation
Applications for Restart2013-07-08
NRA's Approval for basic design2015-07-15
NRA's Approval for detailed design2016-03-23
NRA's Approval for safety program2016-04-19
Start of NRA Pre-service Inspection2016-04-05
Local Consent2015-10-26
Restart2016-08-12
Age:25

PWR  890MWe (gross)
          846MWe (net)

Owner:  

Operator:

Date of order:
1991
Construction Start:
1986-11
Concrete placing:
1990-10-01
Initial Criticality:
1994-02-23
Grid connection:
1994-03-29
Commercial Operation:
1994-12-15
Main contractor:
MHI
Architect Engineer:
Shikoku EPCO/MAPI
Reactor System supplier:
MHI
Reactor Vessel supplier:
MHI
Incore Structure supplier:
MHI
Fuel supplier:
MNF/NFI
Steam raising supplier:
MHI
Turbine generator supplier:
MHI
Civil works:
various
2013-07-08 2013-07-08   2015-07-15 2015-10-26 2016-08-12

New Regulatory Standards came into effect

Applications by Operator

Application for Permission to Install a Reactor
(Basic design)

NRA Approval

Local Consent
(not a legal requirement)

Restart the reactor

  2016-03-23 2016-04-05
Application for Approval of Construction Plan
(Detailed design based on basic design)

NRA Approval

Pre-service Inspection by NRA

Application for Approval of Operational Safety Program
(Matters regarding operations, including operational safety)

NRA Approval

            2016-04-19  
SNS facebooktwitter

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)

23 January, 2020
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)07:47

Recent News

30 June, 2020
“Existing NPPs to Enter Age of 80-Year Operations” JAIF Annual Survey Says
16 June, 2020
Toshiba ESS and Yokohama National University Boost Joint Research to Upgrade Heavy-Ion Cancer Therapy, Using Kanagawa Prefectural Facility
8 June, 2020
NRA Grants Permission to Make Changes to Reactor Installation at HTTR under New Regulatory Standards
22 May, 2020
Sendai-2 Starts Periodic Inspection, with Due Date Imminent to Install Specific Safety Facilities
15 May, 2020
NRA Issues Draft Review Report for Rokkasho Reprocessing Plant
30 April, 2020
Construction Begins of Next Generation Synchrotron Radiation Facility at Tohoku University, to Be Used for Fuel Cells and Pharmaceuticals
27 April, 2020
Superconducting-Coil Tokamak Plasma Test Device (JT-60SA) Installed at Naka Fusion Institute, with Plasma Generation to Begin in Autumn
17 April, 2020
Japan’s CO2 Emissions Fall 4.6% in FY18, Thanks in Part to Restart of NPPs
14 April, 2020
ANRE Begins Hearing from Concerned Parties on Handling of Treated Contaminated Water at Fukushima Daiichi NPPs
14 April, 2020
IAEA Issues Report Reviewing Treated Contaminated Water at Fukushima Daiichi NPPs, Praising Earlier ANRE Report
▲TOP