Mihama-2

Current StatusPermanent shutdown

PWR  500MWe (gross)
          470MWe (net)

Owner:  

Operator:

Date of order:
1968
Construction Start:
1968-12
Concrete placing:
1968-05
Initial Criticality:
1972-04-10
Grid connection:
1972-04
Commercial Operation:
1972-07-25
Closed down:
2015-04-27
Main contractor:
MAPI
Architect Engineer:
Kansai EPCO/MAPI
Reactor System supplier:
WE
Reactor Vessel supplier:
MHI
Incore Structure supplier:
WE
Fuel supplier:
WE
Steam raising supplier:
MHI
Turbine generator supplier:
MHI
Civil works:
various
SNS facebooktwitter

Video

Grossi on Fukushima: Marking a Decade Since the Accident

10 March, 2021
Grossi on Fukushima: Marking a Decade Since the Accident04:11

Recent News

21 January, 2022
New Year’s Greeting by JAIF Chairman Imai
21 January, 2022
Announcement of the 55th JAIF Annual Conference
13 January, 2022
METI Minister Hagiuda Discusses U.S. Nuclear Cooperation, Winter Electricity Supply and Demand
27 December, 2021
TEPCO Submits Application to NRA for Facilities to Deal with ALPS-Treated Water at Fukushima Daiichi
18 November, 2021
METI Minister Speaks to IAEA International Conference on Decade of Progress Since Fukushima Daiichi Accident
15 November, 2021
Nuclear Energy’s Contribution to Achieving SDGs
8 November, 2021
COP26: Prime Minister Kishida Announces Additional Contribution of USD10 Billion for Climate Change Measures
30 October, 2021
Reelection of Suttsu Mayor Means Literature Investigation for HLW Disposal Will Continue
21 October, 2021
Kishida Makes First Visit to Fukushima Since Becoming Prime Minister
15 October, 2021
LDP Adds SMR Development and Nuclear Fusion to NPP Restarts in Its Policy Manifesto
▲TOP