Mihama-3

Current StatusOutage since 2011-05-14
Applications for Restart2015-03-17
NRA's Approval for basic design2016-10-05
NRA's Approval for detailed design2016-10-26
NRA's Approval for safety program2016-11-16
Age:42

PWR  826MWe (gross)
          780MWe (net)

Owner:  

Operator:

Date of order:
1972
Construction Start:
1972-07
Concrete placing:
1972-08
Initial Criticality:
1976-01-28
Grid connection:
1976-02
Commercial Operation:
1976-12-01
Main contractor:
MSK
Architect Engineer:
Kansai EPCO/MAPI
Reactor System supplier:
MHI
Reactor Vessel supplier:
MHI
Incore Structure supplier:
MHI
Fuel supplier:
MNF
Steam raising supplier:
MHI
Turbine generator supplier:
MHI
Civil works:
Hazama/Takenaka
2013-07-08 2015-03-17   2016-10-05    

New Regulatory Standards came into effect

Applications by Operator

Application for Permission to Install a Reactor
(Basic design)

NRA Approval

Local Consent
(not a legal requirement)

Restart the reactor

  2016-10-26  
Application for Approval of Construction Plan
(Detailed design based on basic design)

NRA Approval

Pre-service Inspection by NRA

Application for Approval of Operational Safety Program
(Matters regarding operations, including operational safety)

NRA Approval

            2016-11-16  
SNS facebooktwitter

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, July 2019)

8 July, 2019
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, July 2019)09:17

Recent News

16 August, 2019
Two-day International Forum on Decommissioning Fukushima Daiichi Focuses on Coexistence and Co-prosperity with Local Communities
16 August, 2019
Proponents for Above-ground HLW Management Lose in Chiba University Debate
9 August, 2019
NRA Exchanges Views with President Sakamoto of RFS, Which Pledges to Make Its Utmost Efforts
9 August, 2019
IRID Symposium Held in Fukushima, with Students Explaining Their Research on Fuel Debris Removal
8 August, 2019
TEPCO Decides to Decommission All Four Fukushima Daini Units
8 August, 2019
JAERO President Masumoto Reports to JAEC on Activities and Accumulation of Knowhow in the 50 Years since Establishment
2 August, 2019
Tohoku Electric Power Applies for Approval of Onagawa-1 Decommissioning Plan
2 August, 2019
IEEJ’s 2020 Economic and Energy Outlook Compares Effects of Completing and Not Completing Anti-Terrorism Facilities at Japan’s NPPs
1 August, 2019
JAEC Chairman Oka Remembers IAEA Director General Amano
1 August, 2019
NRA Deliberates Response by Takahama NPPs against Potential Tsunamis Caused by Underwater Landslides
▲TOP