Ohi-4

Current Statusin Operation
Applications for Restart2013-07-08
NRA's Approval for basic design2017-05-24
NRA's Approval for detailed design2017-08-25
NRA's Approval for safety program2017-09-01
Start of NRA Pre-service Inspection2017-09-11
Local Consent2017-11-27
Restart2018-05-09
Age:26

PWR  1180MWe (gross)
          1127MWe (net)

Owner:  

Operator:

Date of order:
1987
Construction Start:
1987-05
Concrete placing:
1988-06
Initial Criticality:
1992-05-28
Grid connection:
1992-06
Commercial Operation:
1993-02-02
Main contractor:
MHI
Architect Engineer:
Kansai EPCO/MAPI
Reactor System supplier:
MHI
Reactor Vessel supplier:
MHI
Incore Structure supplier:
MHI
Fuel supplier:
MNF
Steam raising supplier:
MHI
Turbine generator supplier:
MHI
Civil works:
various
2013-07-08 2013-07-08   2017-05-24 2017-11-27 2018-05-09

New Regulatory Standards came into effect

Applications by Operator

Application for Permission to Install a Reactor
(Basic design)

NRA Approval

Local Consent
(not a legal requirement)

Restart the reactor

  2017-08-25 2017-09-11
Application for Approval of Construction Plan
(Detailed design based on basic design)

NRA Approval

Pre-service Inspection by NRA

Application for Approval of Operational Safety Program
(Matters regarding operations, including operational safety)

NRA Approval

            2017-09-01  
SNS facebooktwitter

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)

23 January, 2020
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)07:47

Recent News

29 January, 2020
JAIF President Takahashi Gives Press Briefing, Describing Court Order Halting the Operation of Ikata-3 as “Regrettable”
23 January, 2020
Finishing Mission in Japan, IAEA’s IRRS Points Out Importance of NRA’s Communicating with Nuclear Industry
21 January, 2020
Evacuation Orders for Futaba, Okuma, Tomioka Towns to Be Partially Lifted in March, with JR Joban Line to Be Completely Reopened for Service
16 January, 2020
Japan’s Nuclear Power Plant Capacity Factor Stood at Just 21.4 Percent Last Year
26 December, 2019
IEEJ’s Supply-Demand Outlook for FY2020 Looks at Effect of Specific Safety Facility Installation Deadlines
25 December, 2019
ANRE Committee Clarifies Options for Treated Contaminated Water at Fukushima Daiichi NPPs, Viewing Both Offshore and Vapor Release Favorably
24 December, 2019
Fuel Removal from Fukushima Daiichi-1 NPP: Large Cover to be Installed First
18 December, 2019
JAEC Begins Hearing from University Personnel on Human Resource Development, Starting with Nagoya and Osaka Universities
13 December, 2019
NRA Approves Decommissioning Plans for Kansai EP’s Ohi-1 and-2
12 December, 2019
JAEA Holds International Forum on Peaceful Use of Nuclear Energy, Nuclear Non-Proliferation and Nuclear Security
▲TOP