Takahama-1

Current StatusOutage since 2011-01-10
Applications for Restart2015-03-17
NRA's Approval for basic design2016-04-20
Age:46

PWR  826MWe (gross)
          780MWe (net)

Owner:  

Operator:

Date of order:
1970
Construction Start:
1970-04
Concrete placing:
1970-04
Initial Criticality:
1974-03-14
Grid connection:
1974-03
Commercial Operation:
1974-11-14
Main contractor:
WE/MSK
Architect Engineer:
Kansai EPCO/Gilbert
Reactor System supplier:
WE/MHI
Reactor Vessel supplier:
MHI
Incore Structure supplier:
WE/MHI
Fuel supplier:
MNF
Steam raising supplier:
MHI
Turbine generator supplier:
MHI
Civil works:
various
2013-07-08 2015-03-17   2016-04-20    

New Regulatory Standards came into effect

Applications by Operator

Application for Permission to Install a Reactor
(Basic design)

NRA Approval

Local Consent
(not a legal requirement)

Restart the reactor

     
Application for Approval of Construction Plan
(Detailed design based on basic design)

NRA Approval

Pre-service Inspection by NRA

Application for Approval of Operational Safety Program
(Matters regarding operations, including operational safety)

NRA Approval

SNS facebooktwitter

Video

Grossi on Fukushima: Marking a Decade Since the Accident

10 March, 2021
Grossi on Fukushima: Marking a Decade Since the Accident04:11

Recent News

17 September, 2021
NRA Permits Shimane-2 under New Regulatory Standards
14 September, 2021
IAEA Deputy Director General Evrard Visits Japan in Advance of Safety Review of ALPS-treated Water
1 September, 2021
Evaluation Report Issued by IAEA’s Review Mission to Fukushima Daiichi: First Visit since 2018
24 August, 2021
METI and IAEA Agree on Further Review Missions to Fukushima Daiichi
4 August, 2021
JAEA Restarts High-Temperature Engineering Test Reactor “HTTR”
2 August, 2021
Information about Fukushima Daiichi NPS Water Treatment
28 July, 2021
METI’s Committee Shows Rough Draft of Next Strategic Energy Plan
2 July, 2021
Mihama-3 Restarted After Decade-long Hiatus: First Restart in Japan of a Reactor Operating Beyond 40 Years
28 June, 2021
Mihama-3 Restarts after Decade-long Hiatus
25 June, 2021
New Canada-Japan Partnership Supports Greater Collaboration to Meet Climate Change Objectives and Net-zero Goals
▲TOP