JAPAN ATOMIC INDUSTRIAL FORUM, INC.

for Japanese

ATOMS in JAPAN

21 August, 2017

NRA Approves Full Water-Shielding Wall at Fukushima Daiichi NPPs

On August 15, the Nuclear Regulation Authority (NRA) of Japan officially approved freezing the remaining approximately seven meters of wall on the west side of the buildings of Units 1-4 of the Fukushima Daiichi Nuclear Power Plants, owned by the Tokyo Electric Power Co. (TEPCO).

This constitutes part of the “frozen-soil shielding wall” project, a major effort to deal with contaminated water by freezing more than 1,500 meters of soil around the units. TEPCO will begin freezing the final portion on August 22, and could complete it in early fall.

Freezing operations began at the end of March 2016. The construction of the wall has cost the nation some JPY35 billion (USD318 million at USD1 = JPY110). It is to be fully operated at long last.

At the Fukushima Daiichi NPPs, groundwater entering the reactor buildings has been coming into contact with melted nuclear fuel and the like from the accident, resulting in an increasing amount of contaminated water. To stop that, ice walls were created underground to reduce the volumes of groundwater flowing into the buildings.

Concern was expressed, however, that when the entire wall was frozen, the level of groundwater around the buildings would become substantially lower, and the level of water in the buildings would be relatively higher, with the flow of water thus being reversed. That would mean that contaminated water would then flow from the buildings.

At an NRA meeting on decommissioning held on June 28, TEPCO explained that it would be able to prevent leakage of the contaminated water by controlling groundwater levels using “subdrain” wells around the buildings, even when there was not much rain at all. The NRA agreed generally to freezing the full wall, and proceeded to verify an action plan submitted by TEPCO.

On August 2, groundwater reached an unexpectedly low level, and there was briefly a possibility of outward leakage of contaminated water at a well near Unit 4. The NRA concluded that it was only local—related to excavation work in the surrounding area—and that there would be negligible effect on the operation of the wall. It then approved the changes to the action plan.

The frozen walls are ice walls in the ground around Units 1 to 4, created by circulating coolant through buried pipes. TEPCO has been carrying out the freezing incrementally.

You should learn more about the “contaminated” water situation there.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)

23 January, 2020
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)07:47

Recent News

22 May, 2020
Sendai-2 Starts Periodic Inspection, with Due Date Imminent to Install Specific Safety Facilities
15 May, 2020
NRA Issues Draft Review Report for Rokkasho Reprocessing Plant
30 April, 2020
Construction Begins of Next Generation Synchrotron Radiation Facility at Tohoku University, to Be Used for Fuel Cells and Pharmaceuticals
27 April, 2020
Superconducting-Coil Tokamak Plasma Test Device (JT-60SA) Installed at Naka Fusion Institute, with Plasma Generation to Begin in Autumn
17 April, 2020
Japan’s CO2 Emissions Fall 4.6% in FY18, Thanks in Part to Restart of NPPs
14 April, 2020
ANRE Begins Hearing from Concerned Parties on Handling of Treated Contaminated Water at Fukushima Daiichi NPPs
14 April, 2020
IAEA Issues Report Reviewing Treated Contaminated Water at Fukushima Daiichi NPPs, Praising Earlier ANRE Report
3 April, 2020
Minamisoma City Releases PR Videos about Plan to Become a “Robot Innovation City”
3 April, 2020
TEPCO Presents Ten-Year Decommissioning Midterm Action Plan for Fukushima Daiichi NPS
27 March, 2020
NRA Issues Draft Review Report for JAEA’s HTTR
▲TOP