NRA Confirms Progress in Inspections at Sendai-1 before Restart

At its regular meeting on July 15, Japan's Nuclear Regulation Authority (NRA) confirmed the state of inspections at the Sendai-1 Nuclear Power Plant (PWR, 890MWe), owned and operated by the Kyushu Electric Power Co. It further approved the coming schedule for the plant.

Sendai NPPs

After it approved a change to the reactor’s basic design in September 2014, the NRA gave its first-ever approval at Sendai-1 to an examination of a reactor’s compatibility with new regulatory standards. Later, in March of this year, it approved the construction work plan (i.e., a fleshed-out design based on the basic design), and approved revisions to the operational safety program two months later in May.

Currently, it is carrying out a pre-service inspection toward the restart of Sendai-1, concurrently with an inspection of Sendai-2. On July 10, Kyushu Electric Power completed its loading of fuel assemblies at Unit 1.

The pre-service inspections, which began on March 30, have looked at the state of reactor buildings, as provided for in the first five clauses of the relevant ordinance. So far, inspection of the items in the first three clauses has been completed at Unit 1. Also, a revised operational safety program came into effect on June 5, after the approval given in May.

Accordingly, from June 8 to 26, the NRA conducted its first safety pre-service inspection of the year to confirm that improved measures for severe accidents and other contingencies were properly reflected in operational safety activities, and that they were being implemented. After that, from July 6 to 14, the NRA inspected operations for loading fuel assemblies into the reactor.

From now on, the NRA will inspect comprehensive drills for severe accidents prior to restarting Sendai-1. It is also redoing a periodic inspection of the unit that had been underway when the new regulatory standards came into effect, so as to confirm that it abides by the new standards, while also looking at items previously inspected.

After listening to explanations from staff of the NRA secretariat responsible for specific inspections, NRA Chairman Shunichi Tanaka said, “Safety must remain our consistent priority to the end, and not merely following a schedule.” That demonstrated his determination for inspections as time progresses, as Japan will soon see the first restart of an NPP that has cleared the new regulatory standards.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)

23 January, 2020
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)07:47

Recent News

30 June, 2020
“Existing NPPs to Enter Age of 80-Year Operations” JAIF Annual Survey Says
16 June, 2020
Toshiba ESS and Yokohama National University Boost Joint Research to Upgrade Heavy-Ion Cancer Therapy, Using Kanagawa Prefectural Facility
8 June, 2020
NRA Grants Permission to Make Changes to Reactor Installation at HTTR under New Regulatory Standards
22 May, 2020
Sendai-2 Starts Periodic Inspection, with Due Date Imminent to Install Specific Safety Facilities
15 May, 2020
NRA Issues Draft Review Report for Rokkasho Reprocessing Plant
30 April, 2020
Construction Begins of Next Generation Synchrotron Radiation Facility at Tohoku University, to Be Used for Fuel Cells and Pharmaceuticals
27 April, 2020
Superconducting-Coil Tokamak Plasma Test Device (JT-60SA) Installed at Naka Fusion Institute, with Plasma Generation to Begin in Autumn
17 April, 2020
Japan’s CO2 Emissions Fall 4.6% in FY18, Thanks in Part to Restart of NPPs
14 April, 2020
ANRE Begins Hearing from Concerned Parties on Handling of Treated Contaminated Water at Fukushima Daiichi NPPs
14 April, 2020
IAEA Issues Report Reviewing Treated Contaminated Water at Fukushima Daiichi NPPs, Praising Earlier ANRE Report
▲TOP