NRA Confirms Progress in Inspections at Sendai-1 before Restart

At its regular meeting on July 15, Japan's Nuclear Regulation Authority (NRA) confirmed the state of inspections at the Sendai-1 Nuclear Power Plant (PWR, 890MWe), owned and operated by the Kyushu Electric Power Co. It further approved the coming schedule for the plant.

Sendai NPPs

After it approved a change to the reactor’s basic design in September 2014, the NRA gave its first-ever approval at Sendai-1 to an examination of a reactor’s compatibility with new regulatory standards. Later, in March of this year, it approved the construction work plan (i.e., a fleshed-out design based on the basic design), and approved revisions to the operational safety program two months later in May.

Currently, it is carrying out a pre-service inspection toward the restart of Sendai-1, concurrently with an inspection of Sendai-2. On July 10, Kyushu Electric Power completed its loading of fuel assemblies at Unit 1.

The pre-service inspections, which began on March 30, have looked at the state of reactor buildings, as provided for in the first five clauses of the relevant ordinance. So far, inspection of the items in the first three clauses has been completed at Unit 1. Also, a revised operational safety program came into effect on June 5, after the approval given in May.

Accordingly, from June 8 to 26, the NRA conducted its first safety pre-service inspection of the year to confirm that improved measures for severe accidents and other contingencies were properly reflected in operational safety activities, and that they were being implemented. After that, from July 6 to 14, the NRA inspected operations for loading fuel assemblies into the reactor.

From now on, the NRA will inspect comprehensive drills for severe accidents prior to restarting Sendai-1. It is also redoing a periodic inspection of the unit that had been underway when the new regulatory standards came into effect, so as to confirm that it abides by the new standards, while also looking at items previously inspected.

After listening to explanations from staff of the NRA secretariat responsible for specific inspections, NRA Chairman Shunichi Tanaka said, “Safety must remain our consistent priority to the end, and not merely following a schedule.” That demonstrated his determination for inspections as time progresses, as Japan will soon see the first restart of an NPP that has cleared the new regulatory standards.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

Grossi on Fukushima: Marking a Decade Since the Accident

10 March, 2021
Grossi on Fukushima: Marking a Decade Since the Accident04:11

Recent News

14 September, 2021
IAEA Deputy Director General Evrard Visits Japan in Advance of Safety Review of ALPS-treated Water
1 September, 2021
Evaluation Report Issued by IAEA’s Review Mission to Fukushima Daiichi: First Visit since 2018
24 August, 2021
METI and IAEA Agree on Further Review Missions to Fukushima Daiichi
4 August, 2021
JAEA Restarts High-Temperature Engineering Test Reactor “HTTR”
2 August, 2021
Information about Fukushima Daiichi NPS Water Treatment
28 July, 2021
METI’s Committee Shows Rough Draft of Next Strategic Energy Plan
2 July, 2021
Mihama-3 Restarted After Decade-long Hiatus: First Restart in Japan of a Reactor Operating Beyond 40 Years
28 June, 2021
Mihama-3 Restarts after Decade-long Hiatus
25 June, 2021
New Canada-Japan Partnership Supports Greater Collaboration to Meet Climate Change Objectives and Net-zero Goals
24 June, 2021
METI Issues New Green Growth Strategy Through Achieving Carbon Neutrality
16 June, 2021
ANRE Sticks to “S+3E”
16 June, 2021
Japanese Cabinet Approves Environmental White Paper 2021
16 June, 2021
LDP Parliamentary Association to Reconfirm Position on Utilization of Nuclear Power
16 June, 2021
Fukui Governor Concerned about Deletion of Reference to “Maximum Utilization” of Nuclear Power
14 June, 2021
Working Group on Offshore Release of Treated Water Meets in Miyagi
14 June, 2021
NRA Considers Policy on Treating Slurry from ALPS, with Local Understanding Essential
11 June, 2021
Japanese Cabinet Approves Energy White Paper 2021
11 June, 2021
Government Omits Description of “Maximum Utilization” of Nuclear Power
9 June, 2021
MNF Hopes to Resume Fuel Production as Early as November
8 June, 2021
TEPCO to Develop Sample Tanks at Fukushima Daiichi to Prepare for Offshore Release of Treated Water
▲TOP