6 July, 2018

NRA Draft Report: Tokai-2 NPP Complies with New Regulatory Standards

On July 4, the Nuclear Regulation Authority (NRA) of Japan issued a review report draft finding that the Tokai-2 Nuclear Power Plant (BWR, 1100MWe), owned and operated by the Japan Atomic Power Company (JAPC), complied with the country’s new regulatory standards for nuclear power plants issued after the March 2001 earthquake and tsunami disaster.

Tokai-2 is the third boiling water reactor (BWR) to be granted permission to make changes to its reactor installation (basic design approval), following TEPCO’s Kashiwazaki Kariwa-6 and -7 NPPs in December 2017. The report draft will be officially approved following a period for public comments.

To protect the reactor from tsunamis, JAPC included an embankment seawall when it filed applications for safety examinations in May 2014. For flood protection, though, the design was changed to a “steel pipe-pile reinforced-concrete tide wall” to guard against repeated run-up tides, as well as to improve seismic margins.

Specifically, the design calls for large-caliber, thick-walled steel pipe piles with the strength to withstand earthquakes and tsunamis, supported by the underlying bedrock. The superstructure, meanwhile, is to be covered by reinforced concrete. The examinations confirmed such characteristics as the bearing strength of the facilities and multiple water stop measures.

The NRA had asked JAPC to consider adding “loss of terminal heat sink as a result of tsunami flooding” as an assumed incident, based on the high water levels to be expected from tsunamis striking Japan’s Pacific coast. Both the seawater intake function and all AC power sources will be lost when tsunami-induced flooding causes the loss of the terminal heat sink beyond standard levels. Moreover, drifting debris in the tsunami water might be scattered around the premises.

Having confirmed the effectiveness of JAPC’s measures to prevent reactor core damage through examinations, the NRA will next refer the draft report to the head of the Ministry of Economy, Trade and Industry (METI), also asking him for his opinion on the intention by the Tokyo Electric Power Co. (TEPCO) to provide financial support to JAPC.

The operation of Tokai-2 has been suspended since the giant earthquake and tsunami that struck eastern Japan on March 11, 2011. Before it can restart the reactor, JAPC must first clear an examination for its operating lifetime to be extended, and to obtain approval of the construction work plan (detailed design approval) by November 30, when the plant’s current 40-year lifetime will expire.

In addition, based on agreements, JAPC will have to obtain consent from Ibaraki Prefecture and the 6 cities and villages—including Tokai Village—that host the site.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

Voices from Nuclear Industry – Contributing to a clean and resilient recovery

3 September, 2020
Voices from Nuclear Industry – Contributing to a clean and resilient recovery03:59

Recent News

3 December, 2020
MHI Launches New Strategy to Achieve Carbon Neutrality by 2050
26 November, 2020
JAIF Releases Results of Fact-finding Survey of Japanese Nuclear Industry for Fiscal 2019: Some Effects Seen of COVID-19
24 November, 2020
Japan’s Energy Supply and Demand in Fiscal 2019 Shows CO2 Emissions Down for Sixth Year in a Row
24 November, 2020
NUMO Accepts Applications from Two Municipalities to Conduct Literature Surveys, Moving Closer Toward Selecting HLW Final Disposal Site
16 November, 2020
Kyushu Electric Power Starts Operating Facilities at Sendai-1 NPP Designed for “Specific Severe Accident” Response—First Time in Japan
13 November, 2020
Japan’s NRA Approves Changes to Mutsu Recyclable-Fuel Storage Center after Confirming Regulatory Compliance
13 November, 2020
Keidanren Announces New Growth Strategy Supporting Advanced Reactor Development
29 October, 2020
New Prime Minister Suga Enthusiastic for Carbon-Free Society by 2050
16 October, 2020
Government’s Strategic Policy Committee Starts Deliberations toward Revision of Strategic Energy Plan
13 October, 2020
NUMO Accepts Suttsu’s Application for Literature Survey in Selecting HLW Final Disposal Site—First Since Release of Map of Scientific Features
▲TOP