5 October, 2015

NRA Talks with Kansai EP about Mihama-3 as Legal Lifetime Nears End

At its regular meeting on September 30, the Nuclear Regulation Authority of Japan (NRA) received a report from its secretariat on the current status of examinations to confirm whether the Mihama-3 Nuclear Power Plant (PWR, 826MWe) was compatible with new regulatory standards. The plant is owned and operated by the Kansai Electric Power Co. (Kansai EP).

Mihama-1 and -2 are left

Because the service period of the plant will reach the 40-year mark on November 30, 2016, both the aforementioned compatibility examination and another one dealing with the extension of the reactor’s lifetime are required under the Reactor Regulation Law before it can be restarted.

According to the report, in March of this year, after Kansai EP had filed applications for compatibility examinations (specifically, applications for approvals to change its reactor installation and revise its operational safety programs) for Mihama-3, eight separate evaluation meetings were held to consider the possible effect of earthquakes, tsunami and volcanoes on the plant, with another two held concerning the plant itself.

As for the former, reviews were made of issues of the geological structure, active faults and seismic vibrations surrounding the site. On August 21, the power company presented data on standard ground motion (Ss). Two weeks later, on September 4, it was confirmed that the assessments of volcanic effects had been evaluated sufficiently in a general manner.

As for the plant-related matters, however, Kansai EP submitted only a very few of the additional materials necessary for the examination by the day of the meeting, holding up the review of the application. It cannot be determined, therefore, whether the required examinations can be completed before the reactor reaches its lifetime limit next year.

Meanwhile, regarding approval of the work plan, the secretariat said that the power company had told it that it would submit an application next month, with additional applications to be filed next February and May. Although the period for legally filing an application to extend Mihama-3’s service period is from September 1 to December 1, no application has been filed as of yet.

The secretariat also said that it would try to examine the reactor more efficiently before approving it, as an extensive review of the application is expected, particularly regarding seismic evaluations.

After receiving the report, NRA Commissioner Toyoshi Fuketa—the man in charge of plant-related examinations—described the situation as “quite serious,” adding that he was “not sure” if it could be done “even if we started working on it full-time tomorrow,” thereby demonstrating his strong sense of crisis.

New Commissioner Nobuhiko Ban, on the other hand, said they could “handle the circumstances,” taking into account the balance with other plants.

Kansai EP has filed applications with the NRA to conduct compatibility examinations on seven of its reactors, namely, Mihama-3, Takahama-1 to -4, and Oi-3 and -4. The NRA will continue to hold discussions with the company’s executives about how to handle the matter.

Additionally, at the same regular meeting on September 30, the NRA approved another report by an expert panel regarding a fault zone of crushed rock within the Mihama site, saying that there was “little possibility” of seismic activity there since the Late Pleistocene.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)

23 January, 2020
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)07:47

Recent News

30 June, 2020
“Existing NPPs to Enter Age of 80-Year Operations” JAIF Annual Survey Says
16 June, 2020
Toshiba ESS and Yokohama National University Boost Joint Research to Upgrade Heavy-Ion Cancer Therapy, Using Kanagawa Prefectural Facility
8 June, 2020
NRA Grants Permission to Make Changes to Reactor Installation at HTTR under New Regulatory Standards
22 May, 2020
Sendai-2 Starts Periodic Inspection, with Due Date Imminent to Install Specific Safety Facilities
15 May, 2020
NRA Issues Draft Review Report for Rokkasho Reprocessing Plant
30 April, 2020
Construction Begins of Next Generation Synchrotron Radiation Facility at Tohoku University, to Be Used for Fuel Cells and Pharmaceuticals
27 April, 2020
Superconducting-Coil Tokamak Plasma Test Device (JT-60SA) Installed at Naka Fusion Institute, with Plasma Generation to Begin in Autumn
17 April, 2020
Japan’s CO2 Emissions Fall 4.6% in FY18, Thanks in Part to Restart of NPPs
14 April, 2020
ANRE Begins Hearing from Concerned Parties on Handling of Treated Contaminated Water at Fukushima Daiichi NPPs
14 April, 2020
IAEA Issues Report Reviewing Treated Contaminated Water at Fukushima Daiichi NPPs, Praising Earlier ANRE Report
▲TOP