Ohi-3 & -4 NPPs Clear Safety Examinations toward Restarts this Autumn

On May 24, the Nuclear Regulation Authority (NRA) officially approved review reports certifying clearance of safety examinations by the Ohi-3 and -4 Nuclear Power Plants (PWRs, 1,180 MWe each) in Fukui Prefecture, owned and operated by the Kansai Electric Power Co. (Kansai EP). Twelve NPPs at six sites have now been approved as meeting the new regulatory standards.

Ohi NPPs: Units 3 & 4 are at the front.

Kansai EP will still have to obtain approvals of construction work plans (detailed design approval), consents from the prefecture and local municipality, and more. It hopes to restart both units as early as this autumn.

All seven NPPs at three sites for which Kansai EP had filed applications for safety examinations by the NRA – Ohi-3 and -4 plus the Takahama-1 through -4 and Mihama-3 NPPs, all in Fukui Prefecture – have now been approved. The company is preparing to apply for its Ohi-1 and -2 NPPs.

Kansai EP submitted its applications to the NRA for safety examinations of Ohi-3 and -4 in July 2013. A major focus of the examinations was the state of geologic faults within the site and the area around it. The company increased standard ground motion (Ss) – the assumed maximum shaking in an earthquake within the premises – to 856 gals (a unit of acceleration) from the previous 700 gals. It eventually managed to obtain approval after strengthening other preparedness for natural disasters, including installation of a seawall against tsunami.

In February 2017, the NRA approved review report drafts after a one-month period for public comments. The NRA concluded that the company’s basic policy on safety measures was compatible with the new regulatory standards.

On May 17, Kansai EP restarted its Takahama-4 (PWR, 870MWe), expecting to resume commercial operation in mid-June. It also plans to restart the Takahama-3 (PWR, 870MWe) in early June.

 

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

Voices from Nuclear Industry – Contributing to a clean and resilient recovery

3 September, 2020
Voices from Nuclear Industry – Contributing to a clean and resilient recovery03:59

Recent News

26 November, 2020
JAIF Releases Results of Fact-finding Survey of Japanese Nuclear Industry for Fiscal 2019: Some Effects Seen of COVID-19
24 November, 2020
Japan’s Energy Supply and Demand in Fiscal 2019 Shows CO2 Emissions Down for Sixth Year in a Row
24 November, 2020
NUMO Accepts Applications from Two Municipalities to Conduct Literature Surveys, Moving Closer Toward Selecting HLW Final Disposal Site
16 November, 2020
Kyushu Electric Power Starts Operating Facilities at Sendai-1 NPP Designed for “Specific Severe Accident” Response—First Time in Japan
13 November, 2020
Japan’s NRA Approves Changes to Mutsu Recyclable-Fuel Storage Center after Confirming Regulatory Compliance
13 November, 2020
Keidanren Announces New Growth Strategy Supporting Advanced Reactor Development
29 October, 2020
New Prime Minister Suga Enthusiastic for Carbon-Free Society by 2050
16 October, 2020
Government’s Strategic Policy Committee Starts Deliberations toward Revision of Strategic Energy Plan
13 October, 2020
NUMO Accepts Suttsu’s Application for Literature Survey in Selecting HLW Final Disposal Site—First Since Release of Map of Scientific Features
12 October, 2020
Nuclear Power Plant and Reactor Exporters’ Principles of Conduct (NuPoC)
▲TOP