Otsu District Court Orders Halt to Operation of Takahama-3 & -4 NPPs

Deciding on a request for a temporary injunction prohibiting operation of the Takahama-3 and -4 Nuclear Power Plants (PWRs, 870MWe each), owned and operated by the Kansai Electric Power Co. (Kansai EP), filed by anti-nuclear local groups in Shiga Prefecture, District Court Judge Yoshihiko Yamamoto on March 9 ruled against their operation.

Takahama-3&4

This is the first judicial decision prohibiting operation of NPPs that had restarted after the accident at the Fukushima Daiichi Nuclear Power Plants. Because a temporary injunction is effective immediately, in contrast to the case of a ruling in a lawsuit, the two units are forced to shutdown. Unless the decision is reversed by a judicial procedure hereafter, Kansai EP may not continue resumption of operation of them.

Confusion is increasing in the circumstances around nuclear power in Japan.

On the same day, Kansai EP released a statement: “We will promptly take steps to file an objection and will do our best to assert and prove the safety of the Takahama-3 and -4 NPPs so as to obtain the lifting of the temporary injunction as soon as possible.”

Both the Takahama-3 and Takahama-4 cleared the safety examinations by the Nuclear Regulation Authority (NRA) in February 2015. Unit 3 was restarted this past January and is in operation at the moment. Unit 4 was restarted in February, but operation was suspended because of a problem occurring immediate after that. Kansai EP submitted to the NRA just today a report on the cause of that problem and the steps it would take to correct it.

Points of contention are standard ground motion (Ss), the intensity of the maximum earthquake assumed for the aseismic design, which Kansai EP put at 700 gals; and the validity of the new regulatory standards for NPPs provided by the NRA. Saying that Kansai EP’s assumption is “not sufficient to secure safety,” the local anti-nuclear group asserted that if an accident occurs, people in Shiga Prefecture would be exposed to radiation and that Lake Biwa would be contaminated to the extent of adversely affecting drinking water in the Kinki Region. They argued that the requirement under the new regulatory standards is too low and, further, that no effective evacuation plan has been issued. Kansai EP rebuts the contention vigorously, saying “safety is secured.”

Concurrently with its request for a temporary injection, the anti-nuclear-side filed a lawsuit, which is pending in same court.

Judge Yamamoto served as the chief judge in a decision on a temporary injunction regarding Takahama-3 and -4 that was made in November 2014, before the restarts. At that time he denied an injunction because restarts were not imminent.

Issues of the two units were also litigated at the Fukui District Court. In April 2015, that court issued a temporary injunction prohibiting restarts, but a different judge reversed the decision and the anti-nuclear group appealed to the Kanazawa Branch of the Nagoya District Court.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, July 2019)

8 July, 2019
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, July 2019)09:17

Recent News

23 January, 2020
Finishing Mission in Japan, IAEA’s IRRS Points Out Importance of NRA’s Communicating with Nuclear Industry
21 January, 2020
Evacuation Orders for Futaba, Okuma, Tomioka Towns to Be Partially Lifted in March, with JR Joban Line to Be Completely Reopened for Service
16 January, 2020
Japan’s Nuclear Power Plant Capacity Factor Stood at Just 21.4 Percent Last Year
26 December, 2019
IEEJ’s Supply-Demand Outlook for FY2020 Looks at Effect of Specific Safety Facility Installation Deadlines
25 December, 2019
ANRE Committee Clarifies Options for Treated Contaminated Water at Fukushima Daiichi NPPs, Viewing Both Offshore and Vapor Release Favorably
24 December, 2019
Fuel Removal from Fukushima Daiichi-1 NPP: Large Cover to be Installed First
18 December, 2019
JAEC Begins Hearing from University Personnel on Human Resource Development, Starting with Nagoya and Osaka Universities
13 December, 2019
NRA Approves Decommissioning Plans for Kansai EP’s Ohi-1 and-2
12 December, 2019
JAEA Holds International Forum on Peaceful Use of Nuclear Energy, Nuclear Non-Proliferation and Nuclear Security
29 November, 2019
NRA Issues Draft Review Report: Onagawa-2 Meets New Regulatory Standards
▲TOP