Otsu District Court Orders Halt to Operation of Takahama-3 & -4 NPPs

Deciding on a request for a temporary injunction prohibiting operation of the Takahama-3 and -4 Nuclear Power Plants (PWRs, 870MWe each), owned and operated by the Kansai Electric Power Co. (Kansai EP), filed by anti-nuclear local groups in Shiga Prefecture, District Court Judge Yoshihiko Yamamoto on March 9 ruled against their operation.

Takahama-3&4

This is the first judicial decision prohibiting operation of NPPs that had restarted after the accident at the Fukushima Daiichi Nuclear Power Plants. Because a temporary injunction is effective immediately, in contrast to the case of a ruling in a lawsuit, the two units are forced to shutdown. Unless the decision is reversed by a judicial procedure hereafter, Kansai EP may not continue resumption of operation of them.

Confusion is increasing in the circumstances around nuclear power in Japan.

On the same day, Kansai EP released a statement: “We will promptly take steps to file an objection and will do our best to assert and prove the safety of the Takahama-3 and -4 NPPs so as to obtain the lifting of the temporary injunction as soon as possible.”

Both the Takahama-3 and Takahama-4 cleared the safety examinations by the Nuclear Regulation Authority (NRA) in February 2015. Unit 3 was restarted this past January and is in operation at the moment. Unit 4 was restarted in February, but operation was suspended because of a problem occurring immediate after that. Kansai EP submitted to the NRA just today a report on the cause of that problem and the steps it would take to correct it.

Points of contention are standard ground motion (Ss), the intensity of the maximum earthquake assumed for the aseismic design, which Kansai EP put at 700 gals; and the validity of the new regulatory standards for NPPs provided by the NRA. Saying that Kansai EP’s assumption is “not sufficient to secure safety,” the local anti-nuclear group asserted that if an accident occurs, people in Shiga Prefecture would be exposed to radiation and that Lake Biwa would be contaminated to the extent of adversely affecting drinking water in the Kinki Region. They argued that the requirement under the new regulatory standards is too low and, further, that no effective evacuation plan has been issued. Kansai EP rebuts the contention vigorously, saying “safety is secured.”

Concurrently with its request for a temporary injection, the anti-nuclear-side filed a lawsuit, which is pending in same court.

Judge Yamamoto served as the chief judge in a decision on a temporary injunction regarding Takahama-3 and -4 that was made in November 2014, before the restarts. At that time he denied an injunction because restarts were not imminent.

Issues of the two units were also litigated at the Fukui District Court. In April 2015, that court issued a temporary injunction prohibiting restarts, but a different judge reversed the decision and the anti-nuclear group appealed to the Kanazawa Branch of the Nagoya District Court.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

Grossi on Fukushima: Marking a Decade Since the Accident

10 March, 2021
Grossi on Fukushima: Marking a Decade Since the Accident04:11

Recent News

15 October, 2021
LDP Adds SMR Development and Nuclear Fusion to NPP Restarts in Its Policy Manifesto
7 October, 2021
Kishida Administration Inaugurated, with New METI Minister Hagiuda Holding Press Conference on Taking Office
6 October, 2021
IAEA Holds 65th General Conference in Vienna, with Japanese Minister of State for Science and Technology Delivering Statement in the General Debate
30 September, 2021
JAEC Releases 2020 White Paper on Nuclear Energy
17 September, 2021
NRA Permits Shimane-2 under New Regulatory Standards
14 September, 2021
IAEA Deputy Director General Evrard Visits Japan in Advance of Safety Review of ALPS-treated Water
1 September, 2021
Evaluation Report Issued by IAEA’s Review Mission to Fukushima Daiichi: First Visit since 2018
24 August, 2021
METI and IAEA Agree on Further Review Missions to Fukushima Daiichi
4 August, 2021
JAEA Restarts High-Temperature Engineering Test Reactor “HTTR”
2 August, 2021
Information about Fukushima Daiichi NPS Water Treatment
28 July, 2021
METI’s Committee Shows Rough Draft of Next Strategic Energy Plan
2 July, 2021
Mihama-3 Restarted After Decade-long Hiatus: First Restart in Japan of a Reactor Operating Beyond 40 Years
28 June, 2021
Mihama-3 Restarts after Decade-long Hiatus
25 June, 2021
New Canada-Japan Partnership Supports Greater Collaboration to Meet Climate Change Objectives and Net-zero Goals
24 June, 2021
METI Issues New Green Growth Strategy Through Achieving Carbon Neutrality
16 June, 2021
ANRE Sticks to “S+3E”
16 June, 2021
Japanese Cabinet Approves Environmental White Paper 2021
16 June, 2021
LDP Parliamentary Association to Reconfirm Position on Utilization of Nuclear Power
16 June, 2021
Fukui Governor Concerned about Deletion of Reference to “Maximum Utilization” of Nuclear Power
14 June, 2021
Working Group on Offshore Release of Treated Water Meets in Miyagi
▲TOP