Science Council of Japan Makes Proposal on HLW Disposal Policy

On April 28, the Science Council of Japan released a policy proposal on the disposal of high-level radioactive waste (HLW). The council issued a proposal two years ago on the same matter, at the request of the Japan Atomic Energy Commission (JAEC). In the current proposal, it presents 12 specific measures on such matters as interim storage and consensus-building, which were previously suggested more generally.

The interim storage of HLW refers to storing it in a retrievable manner during a moratorium period during which technologies will be developed and long-term measures addressed. The proposal puts the moratorium at five decades in principle, with an initial timeline of three decades or so to build consensus, identify suitable locations for final disposal, and select candidate sites.

In the next two decades or so, a final disposal facility will be constructed. At least one interim facility should be located within the distribution zone of a power company with nuclear power plants, but preferably not in a region hosting NPPs, from the viewpoint of “fairly sharing the burden.”

Given that the phrase “interim storage” is also used in the context of the centralized management of waste generated by decontamination work stemming from the accident at the Fukushima Daiichi, the proposal includes a section explaining the difference, as well as its relationship with geological disposal.

The policy proposal emphasizes that HLW interim storage is necessary both to allow the waste to cool before being disposed geologically, and to allow time for activities restoring trust in nuclear power, which will be carried out during the moratorium period.

As for an organizational mechanism toward the building of societal consensus, a committee on comprehensive policy on HLW issues would be legally positioned as a governmental but highly independent, third-party organization, inclusive of the National Governors’ Association and the like.

Under the committee, a national conference would be set up on nuclear waste, emphasizing citizens’ participation, to discuss the desired manner of site selection and consensus-building. All possible candidate sites would have to be listed after examining geologically-detailed information from across the country.

Also, a committee of experts to investigate scientific and technological issues would be formed, composed of experts and specialists in both the natural and social sciences. Its responsibility would be to draw up a list of candidate sites, in addition to carrying out investigations and research on facility management, safety and risk assessment.

The proposal strikes a note of warning against making too hasty a response. Without a clear plan for ensuring storage capacity for HLW to be produced in the future — including interim storage — it says that restarting existing NPPs and constructing new ones would be a “failure in our ethical responsibility to future generations, as well as a violation of the principles of intergenerational equitability.”

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

Grossi on Fukushima: Marking a Decade Since the Accident

10 March, 2021
Grossi on Fukushima: Marking a Decade Since the Accident04:11

Recent News

14 September, 2021
IAEA Deputy Director General Evrard Visits Japan in Advance of Safety Review of ALPS-treated Water
1 September, 2021
Evaluation Report Issued by IAEA’s Review Mission to Fukushima Daiichi: First Visit since 2018
24 August, 2021
METI and IAEA Agree on Further Review Missions to Fukushima Daiichi
4 August, 2021
JAEA Restarts High-Temperature Engineering Test Reactor “HTTR”
2 August, 2021
Information about Fukushima Daiichi NPS Water Treatment
28 July, 2021
METI’s Committee Shows Rough Draft of Next Strategic Energy Plan
2 July, 2021
Mihama-3 Restarted After Decade-long Hiatus: First Restart in Japan of a Reactor Operating Beyond 40 Years
28 June, 2021
Mihama-3 Restarts after Decade-long Hiatus
25 June, 2021
New Canada-Japan Partnership Supports Greater Collaboration to Meet Climate Change Objectives and Net-zero Goals
24 June, 2021
METI Issues New Green Growth Strategy Through Achieving Carbon Neutrality
16 June, 2021
ANRE Sticks to “S+3E”
16 June, 2021
Japanese Cabinet Approves Environmental White Paper 2021
16 June, 2021
LDP Parliamentary Association to Reconfirm Position on Utilization of Nuclear Power
16 June, 2021
Fukui Governor Concerned about Deletion of Reference to “Maximum Utilization” of Nuclear Power
14 June, 2021
Working Group on Offshore Release of Treated Water Meets in Miyagi
14 June, 2021
NRA Considers Policy on Treating Slurry from ALPS, with Local Understanding Essential
11 June, 2021
Japanese Cabinet Approves Energy White Paper 2021
11 June, 2021
Government Omits Description of “Maximum Utilization” of Nuclear Power
9 June, 2021
MNF Hopes to Resume Fuel Production as Early as November
8 June, 2021
TEPCO to Develop Sample Tanks at Fukushima Daiichi to Prepare for Offshore Release of Treated Water
▲TOP