On February 5, the Tokyo Electric Power Co. (TEPCO) began to fill the seaside trench of Unit 3 at the Fukushima Daiichi Nuclear Power Station with special cement (see photo).

The work was carried out as part of the larger project to remove the contaminated water that had accumulated there.

Contaminated water in trenches must be removed before frozen-soil shielding walls can be built. Similar work is underway at the Unit 2 seaside trench.

At Unit 3, TEPCO poured cement into the seaside trench right from the beginning as the first step – a change from the previous method. A total of one million cubic meters, as planned, was poured on the day.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

Voices from Nuclear Industry – Contributing to a clean and resilient recovery

3 September, 2020
Voices from Nuclear Industry – Contributing to a clean and resilient recovery03:59

Recent News

15 September, 2020
Japan’s Cabinet Office to Hold Virtual Side Event on Radiation Cancer Therapy at IAEA General Conference
10 September, 2020
New Report Released on Nuclear Power’s Role in Dealing with Environment Issues
4 September, 2020
Japan’s NRA Says RFS’s Recyclable-Fuel Storage Center Is Compatible with Regulatory Standards
3 September, 2020
JAIF Issues Joint Video Message with Foreign Counterparts
27 August, 2020
METI Minister Kajiyama Stresses Importance of Realizing HLW Final Disposal
7 August, 2020
Nuclear Powered Ship Mutsu Designated as Special “Ship Heritage”
3 August, 2020
On Taking Office as JAIF President
3 August, 2020
Nuclear Energy Buyers Guide in Japan 2020-21 is now available
31 July, 2020
Thoughts on the Decision to Approve Changes to the Reprocessing Business
31 July, 2020
NRA Permits JNFL to Alter Rokkasho Reprocessing Plant, Its Having Complied with New Regulatory Standards
▲TOP