Second Nuclear Fuel Facility Clears NRA’s Safety Examination

At its regular meeting on April 19, Japan's Nuclear Regulation Authority (NRA) approved a review report draft confirming that the uranium enrichment plant owned by Japan Nuclear Fuel Ltd. (JNFL), in Rokkasho Village (Aomori Prefecture) is compatible with new regulatory standards.

JNFL's Uranium Enrichment Plant in 1996

This means that the plant has essentially passed the examination—the second nuclear fuel facility to do so since the new standards took effect. The first was a fuel fabrication plant owned by Global Nuclear Fuel-Japan Co. (GNF-J), in Yokosuka City (Kanagawa Prefecture). The draft report will be made official after receiving input from the head of the Ministry of Economy, Trade and Industry (METI).

The enrichment plant began operation back in 1992. In December 2013, the new regulatory standards came into effect. In the following month—January 2014—JNFL filed an application for the examination.

Under the terms for a grace period for existing facilities not having substantial exposure effects on residents of surrounding areas, the plant was allowed to continue in operation for five years after the new standards came into effect. As a result, part of the plant has continued in operation since then.

Meanwhile, it was revealed last year that the department at JNFL responsible for quality assurance had reported internally that business reform had been completed, whereas in fact it had not been. The NRA thereupon examined anew the company’s internal control system, resulting in a delay in finalizing the review report.

Major examinations have also been completed for JNFL’s spent fuel reprocessing plant and others, all of which are integral to national nuclear fuel cycle policy.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)

23 January, 2020
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)07:47

Recent News

3 August, 2020
On Taking Office as JAIF President
3 August, 2020
Nuclear Energy Buyers Guide in Japan 2020-21 is now available
31 July, 2020
Thoughts on the Decision to Approve Changes to the Reprocessing Business
31 July, 2020
NRA Permits JNFL to Alter Rokkasho Reprocessing Plant, Its Having Complied with New Regulatory Standards
30 June, 2020
“Existing NPPs to Enter Age of 80-Year Operations” JAIF Annual Survey Says
16 June, 2020
Toshiba ESS and Yokohama National University Boost Joint Research to Upgrade Heavy-Ion Cancer Therapy, Using Kanagawa Prefectural Facility
8 June, 2020
NRA Grants Permission to Make Changes to Reactor Installation at HTTR under New Regulatory Standards
22 May, 2020
Sendai-2 Starts Periodic Inspection, with Due Date Imminent to Install Specific Safety Facilities
15 May, 2020
NRA Issues Draft Review Report for Rokkasho Reprocessing Plant
30 April, 2020
Construction Begins of Next Generation Synchrotron Radiation Facility at Tohoku University, to Be Used for Fuel Cells and Pharmaceuticals
▲TOP