JAPAN ATOMIC INDUSTRIAL FORUM, INC.

for Japanese

ATOMS in JAPAN

15 October, 2015

Sendai-2 Restarted

On October 15, the Kyushu Electric Power Co. restarted its Sendai-2 Nuclear Power Plant (PWR, 890MWe). It is the second NPP in Japan, following Sendai-1, restarting under the Nuclear Regulation Authority’s new regulatory standards, which came into effect in July 2013.

Kyushu Electric Power's Sendai NPPs

The unit was restarted at 10:30 a.m. on the 15th and was expected to achieve criticality – stable fission – at around 11:00 p.m. the same day. After the operator commences power generation, the unit will be connected to the grid on October 21, and output will be gradually increased to full in early November. After a final inspection by the NRA, commercial operation should resume in mid-November.

Since the beginning of a periodic inspection in September 2011, operation of the Sendai-2 had been suspended for four years and a month. Because the Sendai-1 (PWR, 890MWe), which resumed operation in August after a shutdown of four years and three months, experienced a problem with seawater leaking into a condenser while output was being increased, Kyushu Electric Power carried out an inspection of condenser piping, etc., at Sendai-2 during nine days in September. The company intends to continue prudently.

In addition to the Sendai-1 and -2 NPPs, three other NPPs have cleared the NRA’s safety examinations: the Takahama-3 and -4, owned and operated by Kansai Electric Power Co., and the Ikata-3, owned and operated by the Shikoku Electric Power Co.

Takahama-3 and -4 will not, however, be able to restart unless a temporary injunction prohibiting restart, issued by the Fukui District Court, is lifted.

As for Ikata-3, although the Ikata Town Assembly and the Ehime Prefectural Assembly have both agreed to a restart, the pre-service inspection has not begun, and actual restart of the unit is expected in early 2016 or later.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)

23 January, 2020
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)07:47

Recent News

30 June, 2020
“Existing NPPs to Enter Age of 80-Year Operations” JAIF Annual Survey Says
16 June, 2020
Toshiba ESS and Yokohama National University Boost Joint Research to Upgrade Heavy-Ion Cancer Therapy, Using Kanagawa Prefectural Facility
8 June, 2020
NRA Grants Permission to Make Changes to Reactor Installation at HTTR under New Regulatory Standards
22 May, 2020
Sendai-2 Starts Periodic Inspection, with Due Date Imminent to Install Specific Safety Facilities
15 May, 2020
NRA Issues Draft Review Report for Rokkasho Reprocessing Plant
30 April, 2020
Construction Begins of Next Generation Synchrotron Radiation Facility at Tohoku University, to Be Used for Fuel Cells and Pharmaceuticals
27 April, 2020
Superconducting-Coil Tokamak Plasma Test Device (JT-60SA) Installed at Naka Fusion Institute, with Plasma Generation to Begin in Autumn
17 April, 2020
Japan’s CO2 Emissions Fall 4.6% in FY18, Thanks in Part to Restart of NPPs
14 April, 2020
ANRE Begins Hearing from Concerned Parties on Handling of Treated Contaminated Water at Fukushima Daiichi NPPs
14 April, 2020
IAEA Issues Report Reviewing Treated Contaminated Water at Fukushima Daiichi NPPs, Praising Earlier ANRE Report
▲TOP