Sendai-2 Starts Periodic Inspection, with Due Date Imminent to Install Specific Safety Facilities

Since March of this year, a periodic inspection has been underway at the Sendai-1 (PWR, 890 MW), owned and operated by the Kyushu Electric Power Co.. On May 20, the company began a similar inspection of its Sendai-2 (PWR, 890 MW), the period for which was moved up because of the approaching deadline for the installation of facilities—termed specific safety facilities—to respond to specific severe accidents, including terrorist attacks, and which are mandated under the new regulatory standards for Japan’s nuclear power plants (NPPs).

Five-year grace periods for the installation of such facilities were granted from the date of approval of both plants’ construction work plans (detailed design approvals)—March 18 and May 22, 2015, for Sendai-1 and -2, respectively—so the deadline for Sendai-2 will expire soon. The two units had already cleared their examinations under the new regulatory standards ahead of others nationwide, having resumed operation in August and October 2015, respectively.

The periodic inspection of Sendai-2 is expected to take approximately nine months, ending next year. In addition to work to install the specific safety facilities, refueling of the unit will also take place, as well as the installation of a permanent direct-current power supply system (the third one), as required under the new regulatory standards.

On April 30, Kyushu Electric President Kazuhiro Ikebe, at a press conference to address the power utility’s financial results for FY19, expressed concern for the effects of the coronavirus (COVID-19) pandemic on the country’s electricity industry. Referring to the FY20 earnings forecast, he contrasted the present situation unfavorably with the financial crisis of more than a decade ago, saying, “Now, even the department stores are closed, unlike before.”

Ikebe repeatedly stressed that the outlook for Japan’s entire economy was uncertain, estimating the increased costs for substitute fuel, on account of the suspension of operations at the Sendai-1 and -2, at about JPY25 billion (USD230 million at USD1=JPY108).

According to a report on actual electricity supply and demand, released by Japan’s Organization for Cross-regional Coordination of Transmission Operators, (OCCTO) on May 15, the capacity margin for July and August 2020 in the Kyushu area is forecast to be around 8 percent, enough to secure supply capabilities for the peak summer demand period.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

Grossi on Fukushima: Marking a Decade Since the Accident

10 March, 2021
Grossi on Fukushima: Marking a Decade Since the Accident04:11

Recent News

18 November, 2021
METI Minister Speaks to IAEA International Conference on Decade of Progress Since Fukushima Daiichi Accident
15 November, 2021
Nuclear Energy’s Contribution to Achieving SDGs
8 November, 2021
COP26: Prime Minister Kishida Announces Additional Contribution of USD10 Billion for Climate Change Measures
30 October, 2021
Reelection of Suttsu Mayor Means Literature Investigation for HLW Disposal Will Continue
21 October, 2021
Kishida Makes First Visit to Fukushima Since Becoming Prime Minister
15 October, 2021
LDP Adds SMR Development and Nuclear Fusion to NPP Restarts in Its Policy Manifesto
7 October, 2021
Kishida Administration Inaugurated, with New METI Minister Hagiuda Holding Press Conference on Taking Office
6 October, 2021
IAEA Holds 65th General Conference in Vienna, with Japanese Minister of State for Science and Technology Delivering Statement in the General Debate
30 September, 2021
JAEC Releases 2020 White Paper on Nuclear Energy
17 September, 2021
NRA Permits Shimane-2 under New Regulatory Standards
14 September, 2021
IAEA Deputy Director General Evrard Visits Japan in Advance of Safety Review of ALPS-treated Water
1 September, 2021
Evaluation Report Issued by IAEA’s Review Mission to Fukushima Daiichi: First Visit since 2018
24 August, 2021
METI and IAEA Agree on Further Review Missions to Fukushima Daiichi
4 August, 2021
JAEA Restarts High-Temperature Engineering Test Reactor “HTTR”
2 August, 2021
Information about Fukushima Daiichi NPS Water Treatment
28 July, 2021
METI’s Committee Shows Rough Draft of Next Strategic Energy Plan
2 July, 2021
Mihama-3 Restarted After Decade-long Hiatus: First Restart in Japan of a Reactor Operating Beyond 40 Years
28 June, 2021
Mihama-3 Restarts after Decade-long Hiatus
25 June, 2021
New Canada-Japan Partnership Supports Greater Collaboration to Meet Climate Change Objectives and Net-zero Goals
24 June, 2021
METI Issues New Green Growth Strategy Through Achieving Carbon Neutrality
▲TOP