20 May, 2021

Takahama-1 and -2 and Mihama-3 NPPs Move to 60-Year Operation

On May 12, the Kansai Electric Power Co. (Kansai EP) announced its plans for restarting its Takahama-1 and -2 (PWRs, 826 MWe each) and Mihama-3 (PWR, 826 MWe) Nuclear Power Plants (NPPs). It marks the first time in Japan that commercial reactors will have been restarted after obtaining permission to operate for sixty years.

Shiro Arai

I would like to express my gratitude here to the people in each locality for their understanding on the restarting of the units whose operating lifetimes have been extended, and my respect to all the involved parties for their efforts toward the restart of the reactors.

In addition to periodic inspections approximately once a year, NPPs in Japan are subject to safety reviews every ten years in order to evaluate their safety and reliability. Operators are also required to conduct technological aging evaluations of important safety-related equipment and structures when an NPP reaches thirty years since starting operations, and every ten years thereafter.

Based on those results, a long-term plan for maintenance and management is issued in order to deal with the effects of aging.

Moreover, under the new regulatory standards, when operation reaches forty years, a special inspection is required in addition to ordinary inspections and examinations for the purpose of checking the soundness of the reactor vessel, reactor containment vessel and concrete structures, which would not be replaced but only disqualified.

Based on the aging evaluations, including the results of the special inspection, the operation of the unit for the extended period can be confirmed to be done without any problems.

Having entered service in the 1970’s, the three NPPs mentioned above underwent special inspections and technological aging evaluations prior to completing forty years of operation, confirming their ability to maintain soundness.

Around the world, operating lifetimes of existing reactors are being extended after similar confirmations of soundness. In the United States, in particular, eighty-six NPPs of the total number of ninety-four reactors operating—or 91%—have obtained permission to operate for sixty years. Six of those eighty-six have already been approved for eighty years of operation, and forty-six are already being operated beyond forty years.

A backdrop can be cited for that, beyond the technology and knowledge base to secure safety: namely, nuclear power’s history and potential for reliably supplying low-cost, low-carbon electricity, while remaining unaffected by weather and other factors.

The International Energy Agency (IEA), too, calls nuclear power essential to reduce carbon dioxide (CO2) emissions, which present an imminent global threat, and says that operating existing NPPs beyond forty years is the most economical option among low-carbon power sources.

Approximately 6.75 million tons of CO2 per year could be reduced by operating the Takahama-1 and -2 and Mihama-3 NPPs. That alone is equivalent to 17.6% of the 38.44 million tons that Kansai EP emitted in FY19.

We are confident that Kansai EP will carry out activities toward restarting the reactors, putting a priority on safety. We are also confident that following their restart, the power utility will continue to accumulate a record of performance demonstrating the stability of supply and the reduction of emissions.

Ongoing, thoughtful dialogues with local municipalities and people in the region are also expected to occur.

Shiro Arai, President, JAIF

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

Grossi on Fukushima: Marking a Decade Since the Accident

10 March, 2021
Grossi on Fukushima: Marking a Decade Since the Accident04:11

Recent News

16 June, 2021
ANRE Sticks to “S+3E”
16 June, 2021
Japanese Cabinet Approves Environmental White Paper 2021
16 June, 2021
LDP Parliamentary Association to Reconfirm Position on Utilization of Nuclear Power
16 June, 2021
Fukui Governor Concerned about Deletion of Reference to “Maximum Utilization” of Nuclear Power
14 June, 2021
Working Group on Offshore Release of Treated Water Meets in Miyagi
14 June, 2021
NRA Considers Policy on Treating Slurry from ALPS, with Local Understanding Essential
11 June, 2021
Japanese Cabinet Approves Energy White Paper 2021
11 June, 2021
Government Omits Description of “Maximum Utilization” of Nuclear Power
9 June, 2021
MNF Hopes to Resume Fuel Production as Early as November
8 June, 2021
TEPCO to Develop Sample Tanks at Fukushima Daiichi to Prepare for Offshore Release of Treated Water
8 June, 2021
Opinions Differ Within Japan’s Governing Coalition Concerning Nuclear Power
8 June, 2021
Local Concerns About Unfounded Fears and Rumors on Offshore Release of Treated Water
7 June, 2021
JEMA Proposes that Nuclear Power Be Maintained at a Certain Scale
7 June, 2021
IHI to Participate in NuScale’s SMR Project
4 June, 2021
FEPC Declares for “Zero Emissions”
4 June, 2021
Support Grows Within LDP for Nuclear Power
2 June, 2021
JAIF Reports to JAEC on JAIF Annual Conference
2 June, 2021
Japan’s Power Industry Workers Union Calls for Prudence toward the Closure of Coal-fired Power Plants
2 June, 2021
Japan’s Advisory Committee Discusses Supply-and-Demand Measures in Summer and Winter 2021
1 June, 2021
Preparations Continue Toward Restarting Tokai-2 NPP
▲TOP