Takahama-4 to Restart in May, First Such Case Following Court Ruling to Suspend Operation

On April 25, President Shigeki Iwane of Kansai Electric Power Co. (Kansai EP) met with Governor Issei Nishikawa of Fukui Prefecture at the prefectural offices in Fukui City, telling him that the Takahama-4 Nuclear Power Plant (PWR, 870MWe), located in the prefecture, would be restarted in mid-May, and Unit 3 (PWR, 870MWe) in the first part of June. It will be the first time that a nuclear power plant will be restarted in Japan after its operation was suspended owing to a court decision.

Takahama-3&4

If plans proceed as planned, it will be the first time the two units have operated in one year and three months. That would bring the total of domestic NPPs in operation to five, including Sendai-1 and -2 of the Kyushu Electric Power Co. (Kagoshima Prefecture), and Ikata-3 of the Shikoku Electric Power Co. (Ehime Prefecture). Kansai EP will begin loading fuel to Unit 4 on April 28.

According to the schedule, Unit 4 will start power generation and connect to the grid at the end of May, shifting to commercial operation in the middle of June. Meanwhile, fuel will be loaded into Unit 3 in mid-May, with grid connection targeted to begin in early June, and commercial operation in early July. The two units were each loaded with 157 fuel assemblies, of which four in Unit 4 and 24 in Unit 3 consists of MOX fuel.

The two units had been restarted in January and February of last year, but were both suspended in March 2016, due to a temporary disposition ruling by the Otsu District Court. In March of this year, the Osaka High Court approved Kansai EP’s appeal, canceling the provisional disposition, bringing the reactors into a legally operable state.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)

23 January, 2020
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)07:47

Recent News

30 June, 2020
“Existing NPPs to Enter Age of 80-Year Operations” JAIF Annual Survey Says
16 June, 2020
Toshiba ESS and Yokohama National University Boost Joint Research to Upgrade Heavy-Ion Cancer Therapy, Using Kanagawa Prefectural Facility
8 June, 2020
NRA Grants Permission to Make Changes to Reactor Installation at HTTR under New Regulatory Standards
22 May, 2020
Sendai-2 Starts Periodic Inspection, with Due Date Imminent to Install Specific Safety Facilities
15 May, 2020
NRA Issues Draft Review Report for Rokkasho Reprocessing Plant
30 April, 2020
Construction Begins of Next Generation Synchrotron Radiation Facility at Tohoku University, to Be Used for Fuel Cells and Pharmaceuticals
27 April, 2020
Superconducting-Coil Tokamak Plasma Test Device (JT-60SA) Installed at Naka Fusion Institute, with Plasma Generation to Begin in Autumn
17 April, 2020
Japan’s CO2 Emissions Fall 4.6% in FY18, Thanks in Part to Restart of NPPs
14 April, 2020
ANRE Begins Hearing from Concerned Parties on Handling of Treated Contaminated Water at Fukushima Daiichi NPPs
14 April, 2020
IAEA Issues Report Reviewing Treated Contaminated Water at Fukushima Daiichi NPPs, Praising Earlier ANRE Report
▲TOP