JAPAN ATOMIC INDUSTRIAL FORUM, INC.

for Japanese

ATOMS in JAPAN

5 June, 2019

TEPCO Considering New Plan to Remove Spent Fuel from Fukushima Daiichi-2

On May 30, the Tokyo Electric Power Co. (TEPCO) released a progress report on the decommissioning work taking place at the Fukushima Daiichi Nuclear Power Plants.

At Unit 2, TEPCO still expects to begin removing fuel from the spent fuel pool sometime in FY23 (April 2023 to March 2024). Now, given the reduced radiation levels inside the operating floor of the reactor building found in investigations conducted over the winter, TEPCO is also considering a third approach to the removal, in addition to two approaches that both involve demolishing the upper part of the operating floor.

In the new approach, only as little of the floor as possible would be removed, with an assembly base for removal work to be built on the south side of the operating floor, allowing access to the inside of the floor.

At a press conference, President Akira Ono of the Fukushima Daiichi Decontamination & Decommissioning Engineering Company explained the new thinking. The Unit 2 reactor building, he said, had been spared an internal hydrogen explosion, and by making proper use of it now, the risk of release of radioactive materials can be substantially controlled.

Moving forward, the three fuel-removal approaches will be evaluated in a comprehensive manner considering such matters as dust-suppression measures, the reduction in workers’ exposure doses, rainwater measures, and the influences on other decommissioning work. TEPCO will make its choice of the final approach by the end of FY19 (March 31, 2020).

Although the dismantling of the exhaust stack for Units 1 and 2—part of efforts to improve the surrounding environment—was to have been launched on May 20, it ended up being postponed two months. During the verification process that took place after the crane was assembled, the distance between the crane’s hook and the top of the stack was found to be different from what was planned. To ensure the suspension height, the sub-base needs to be altered, necessitating the two months’ delay.

In way of explanation, President Ono cited several factors, including failures in the division of roles among partner companies, and those involving checking procedures at the site, among others. The work is now expected to start around the end of July and finish in the fourth quarter of FY19 (namely, January to March 2020). He said that TEPCO intended to carry out the process safety and steadily from now on.

In another piece of news, as part of an effort to improve its emergency responses, TEPCO temporarily stopped injecting water into Unit 2 on May 13 in a short test to reconfirm that the temperatures at the bottom of the reactor pressure vessel (RPV) would generally remain within a predicted range. Meanwhile, sampling has been proceeding inside of the containment vessels at Units 1 to 3.

According to particle analyses by electron microscopes focusing on uranium, carried out during the previous fiscal year (April 2018 to March 2019), two types of particles were identified: particles containing almost no zirconium, which are used for fuel cladding, and particles containing substantial zirconium. That information will contribute to analyses of fuel debris samples, as well as to a determination of how to deal with it.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, July 2019)

8 July, 2019
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, July 2019)09:17

Recent News

23 January, 2020
Finishing Mission in Japan, IAEA’s IRRS Points Out Importance of NRA’s Communicating with Nuclear Industry
21 January, 2020
Evacuation Orders for Futaba, Okuma, Tomioka Towns to Be Partially Lifted in March, with JR Joban Line to Be Completely Reopened for Service
16 January, 2020
Japan’s Nuclear Power Plant Capacity Factor Stood at Just 21.4 Percent Last Year
26 December, 2019
IEEJ’s Supply-Demand Outlook for FY2020 Looks at Effect of Specific Safety Facility Installation Deadlines
25 December, 2019
ANRE Committee Clarifies Options for Treated Contaminated Water at Fukushima Daiichi NPPs, Viewing Both Offshore and Vapor Release Favorably
24 December, 2019
Fuel Removal from Fukushima Daiichi-1 NPP: Large Cover to be Installed First
18 December, 2019
JAEC Begins Hearing from University Personnel on Human Resource Development, Starting with Nagoya and Osaka Universities
13 December, 2019
NRA Approves Decommissioning Plans for Kansai EP’s Ohi-1 and-2
12 December, 2019
JAEA Holds International Forum on Peaceful Use of Nuclear Energy, Nuclear Non-Proliferation and Nuclear Security
29 November, 2019
NRA Issues Draft Review Report: Onagawa-2 Meets New Regulatory Standards
▲TOP