TEPCO Decides to Decommission All Four Fukushima Daini Units

On July 31, the Tokyo Electric Power Co. (TEPCO) decided to decommission all four units (BWRs, 1,100MWe each) at the Fukushima Daini Nuclear Power Plants. In June 2018, TEPCO President Tomoaki Kobayakawa had visited Governor Masao Uchibori of Fukushima Prefecture and conveyed the company’s intention then to address decommissioning all the units.

TEPCO's Fukushima Daini NPPs

In making the decision now, TEPCO said it would face the challenges with all sincerity–as it is doing at the Fukushima Daiichi NPPs–so as to ensure peace of mind for the people in the region. It basic principles and objectives, it said, would be: (1) securing adequate human resources (including for Fukushima Daiichi), (2) enabling safe decommissioning, and (3) contributing to industrial development in the region.

In ordinary circumstances, TEPCO would expect the decommissioning of such units to take about 30 years. In this case, however, given that the decommissioning of Fukushima Daiichi will continue simultaneously, it expects to require more than forty years to complete the decommissioning of all four units at Fukushima Daini.

In the process, the power company intends to construct facilities for dry-cask interim storage of the approximately 10,000 fuel assemblies now at the Daini site, carry out a planned removal of those assemblies from the spent fuel pools, and attempt to remove all spent fuel from the prefecture as early as possible, by the end of the decommissioning.

Unit 1 at the Fukushima Daini began commercial operation in 1982, and all four units were in service by 1987. All units subsequently shut down after the giant earthquake that struck eastern Japan on March 11, 2011. When that occurred, then Site Director Naohiro Masuda (currently president of Japan Nuclear Fuel Ltd.) led the successful effort to bring the situation under control.

At a regular press conference on July 31, Chairman Toyoshi Fuketa of the Nuclear Regulation Authority of Japan (NRA) pointed out that decommissioning of the four reactors was“quite a major project,” and said that the NRA would “keep careful watch” so that it would not affect decommissioning work at the Fukushima Daiichi NPPs.

Looking back on the situation at the time of the earthquake, he said that “preparedness at Fukushima Daini was not necessarily sufficient,” and that “if proper instructions had not been given at the site, the situation would have been more serious.” As a lesson from the accident, he stressed the importance of leadership in emergencies.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)

23 January, 2020
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, Jan. 2020)07:47

Recent News

7 August, 2020
Nuclear Powered Ship Mutsu Designated as Special “Ship Heritage”
3 August, 2020
On Taking Office as JAIF President
3 August, 2020
Nuclear Energy Buyers Guide in Japan 2020-21 is now available
31 July, 2020
Thoughts on the Decision to Approve Changes to the Reprocessing Business
31 July, 2020
NRA Permits JNFL to Alter Rokkasho Reprocessing Plant, Its Having Complied with New Regulatory Standards
30 June, 2020
“Existing NPPs to Enter Age of 80-Year Operations” JAIF Annual Survey Says
16 June, 2020
Toshiba ESS and Yokohama National University Boost Joint Research to Upgrade Heavy-Ion Cancer Therapy, Using Kanagawa Prefectural Facility
8 June, 2020
NRA Grants Permission to Make Changes to Reactor Installation at HTTR under New Regulatory Standards
22 May, 2020
Sendai-2 Starts Periodic Inspection, with Due Date Imminent to Install Specific Safety Facilities
15 May, 2020
NRA Issues Draft Review Report for Rokkasho Reprocessing Plant
▲TOP