TEPCO Presents Ten-Year Decommissioning Midterm Action Plan for Fukushima Daiichi NPS

On March 27, the Tokyo Electric Power Co. (TEPCO) released its Decommissioning Midterm Action Plan 2020, describing the main work processes to be conducted in the decommissioning of the Fukushima Daiichi Nuclear Power Plants (NPPs) through the end of 2031 or so.

The so-called “mid-and-long-term roadmap” toward the decommissioning of the Fukushima Daiichi NPPs—describing the specific steps and concrete measures to be taken until decommissioning is completed—was revised at the end of 2019, based on technical proposals by the Nuclear Damage Compensation and Decommissioning Facilitation Corporation (NDF). The roadmap also covers the removal of spent fuel from dedicated pools and the start of the removal of the fuel debris.

To facilitate the planning to achieve the roadmap’s goals, the Decommissioning Midterm Action Plan 2020 presents specific actions to be taken over a decade or so in dealing with the contaminated water, the removal of spent fuel from spent fuel pools, the removal of fuel debris, and measures to deal with waste. The plan is expected to be reviewed every year, and will be adjusted based on future progress.

According to the action plan, the fuel removal currently being undertaken from the spent fuel pool at Unit 3 should be completed during the current fiscal year (that is, by March 31, 2021). According to the roadmap, the removal of spent fuel at Units 1 and 2 is expected to begin in FY28 and FY26, respectively. The removal of the fuel debris is expected to begin sometime in FY21 (starting in April 2021), beginning with Unit 2.

At a press conference on March 27, President Akira Ono of the Fukushima Daiichi Decontamination & Decommissioning Engineering Company, emphasized the importance of carrying out the Decommissioning Midterm Action Plan 2020 “safely and steadily,” looking ahead to a reorganization in April.

TEPCO also announced its promise to Fukushima that “reconstruction and decommissioning will proceed together.” Citing TEPCO’s three slogans of Open, Creation, and Carrying Out, Ono mentioned its determination to strive toward Fukushima’s reconstruction through the long-term decommissioning. Saying that the power utility wanted to deal with local companies directly, he said that it would soon prepare materials explaining the contents of work and technologies required from now on, helping those companies participate in designing the equipment and facilities needed to remove the debris.

Meanwhile, on March 24, TEPCO released a preliminary draft of its plan to dispose of treated water at the Fukushima Daiichi NPPs in response to a report issued in December by a committee of the Agency for Natural Resources & Energy (ANRE) under the Ministry of Economy, Trade and Industry (METI).

Regarding vapor release and offshore release, which had been deemed “practical means” in the ANRE committee’s report, Ono said that the company expected to take “two years or so” for implementation, using that time to prepare equipment and materials, obtaining approvals, and other matters. He also said that TEPCO would work on the detailed designs once the government decides its policy.

He also said the company would aim at communicating in a way “to share information accurately,” emphasizing his determination to work on measures to prevent unfounded rumors and fears.

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

Grossi on Fukushima: Marking a Decade Since the Accident

10 March, 2021
Grossi on Fukushima: Marking a Decade Since the Accident04:11

Recent News

18 November, 2021
METI Minister Speaks to IAEA International Conference on Decade of Progress Since Fukushima Daiichi Accident
15 November, 2021
Nuclear Energy’s Contribution to Achieving SDGs
8 November, 2021
COP26: Prime Minister Kishida Announces Additional Contribution of USD10 Billion for Climate Change Measures
30 October, 2021
Reelection of Suttsu Mayor Means Literature Investigation for HLW Disposal Will Continue
21 October, 2021
Kishida Makes First Visit to Fukushima Since Becoming Prime Minister
15 October, 2021
LDP Adds SMR Development and Nuclear Fusion to NPP Restarts in Its Policy Manifesto
7 October, 2021
Kishida Administration Inaugurated, with New METI Minister Hagiuda Holding Press Conference on Taking Office
6 October, 2021
IAEA Holds 65th General Conference in Vienna, with Japanese Minister of State for Science and Technology Delivering Statement in the General Debate
30 September, 2021
JAEC Releases 2020 White Paper on Nuclear Energy
17 September, 2021
NRA Permits Shimane-2 under New Regulatory Standards
14 September, 2021
IAEA Deputy Director General Evrard Visits Japan in Advance of Safety Review of ALPS-treated Water
1 September, 2021
Evaluation Report Issued by IAEA’s Review Mission to Fukushima Daiichi: First Visit since 2018
24 August, 2021
METI and IAEA Agree on Further Review Missions to Fukushima Daiichi
4 August, 2021
JAEA Restarts High-Temperature Engineering Test Reactor “HTTR”
2 August, 2021
Information about Fukushima Daiichi NPS Water Treatment
28 July, 2021
METI’s Committee Shows Rough Draft of Next Strategic Energy Plan
2 July, 2021
Mihama-3 Restarted After Decade-long Hiatus: First Restart in Japan of a Reactor Operating Beyond 40 Years
28 June, 2021
Mihama-3 Restarts after Decade-long Hiatus
25 June, 2021
New Canada-Japan Partnership Supports Greater Collaboration to Meet Climate Change Objectives and Net-zero Goals
24 June, 2021
METI Issues New Green Growth Strategy Through Achieving Carbon Neutrality
▲TOP