JAPAN ATOMIC INDUSTRIAL FORUM, INC.

for Japanese

ATOMS in JAPAN

2 August, 2019

Tohoku Electric Power Applies for Approval of Onagawa-1 Decommissioning Plan

On July 29, the Tohoku Electric Power Co. filed an application with the Nuclear Regulation Authority (NRA) of Japan for approval of the decommissioning plan for its Onagawa-1 Nuclear Power Plant (BWR, 524MWe, commissioned in June 1984). Also, three days earlier, on July 26, the company requested preliminary talks with Miyagi Prefecture, Onagawa Town and Ishinomaki City under nuclear safety agreements with the respective siting municipalities.

Onagawa-1 had originally been shut down in the wake of the giant earthquake that struck eastern Japan on March 11, 2011. In October 2018, Tohoku Electric Power decided to decommission the reactor after a comprehensive review of the major technological challenges involved were it to be restarted, such as measures to enhance safety, a consideration of the number of years it had been in operation, and issues related to power generation.

The entire decommissioning process is divided into four stages, as follows: (1) preparation for dismantling, (2) the dismantling and removal of facilities and equipment in the area surrounding the reactor, (3) the dismantling and removal of facilities and equipment in the reactor area, and (4) the dismantling and removal of the reactor building and other structures.

The final completion of the process is put at more than three decades from now, at FY53 (April 2053 to March 2054). During the stage of preparation for dismantling—the period from approval of the decommissioning plan to FY27—all of the 821 spent fuel assemblies currently stored in the Unit 1 spent fuel pool will be transferred to and stored in the Unit 3 spent fuel pool.

Once decommissioning is complete, the fuel assemblies will then be transferred to the licensee for reprocessing activities, together with the 161 fuel assemblies from Unit 1 that are now being stored at the spent fuel pools of Units 2 and 3.

Of the approximately 300,000 tons of dismantling waste expected as a result of the decommissioning, about 18,500 tons will be solid radioactive waste. About 12,400 tons of the latter amount is expected to be below a designated clearance level (that is, not requiring handling as radioactive material) and will be recycled to the maximum extent, following prescribed procedures under relevant laws. The total cost for dismantling is estimated at JPY41.9 billion (US$380 million at USD1=JPY110).

Additionally, of the total of 14 NPPs currently designated for decommissioning (excluding all units at Fukushima Daiichi and Daini), decommissioning plans for nine reactors have already been approved by the NRA, as follows:

  • Tokai-2 and Tsuruga-1 (Japan Atomic Power Company)
  • Hamaoka-1 and -2 (Chubu Electric Power Co.)
  • Mihama-1 and -2 (Kansai Electric Power Co.)
  • Shimane-1 (Chugoku Electric Power Co.)
  • Ikata-1 (Shikoku Electric Power Co.)
  • Genkai-1 (Kyushu Electric Power Co.)

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, July 2019)

8 July, 2019
“The current situation at Fukushima Daiichi NPS” -From 3.11 toward the future- (ver, July 2019)09:17

Recent News

13 December, 2019
NRA Approves Decommissioning Plans for Kansai EP’s Ohi-1 and-2
12 December, 2019
JAEA Holds International Forum on Peaceful Use of Nuclear Energy, Nuclear Non-Proliferation and Nuclear Security
29 November, 2019
NRA Issues Draft Review Report: Onagawa-2 Meets New Regulatory Standards
28 November, 2019
RIKEN Unveils Transportable Compact Neutron Source System
27 November, 2019
JAIF Releases Results of Fact-Finding Survey of Japanese Nuclear Industry for Fiscal 2018
26 November, 2019
Hitachi Receives Order from Mayo Clinic to Build First Carbon Ion Treatment System in North America
25 November, 2019
Keidanren: Japan’s Commitment to Low-Carbon Society Shows NPP Restarts Helped Reduce CO2 Emissions in Fiscal 2018
21 November, 2019
TEPCO Announces Timeline for Storage and Disposal of Treated Contaminated Water at Fukushima Daiichi
15 November, 2019
JAEA Holds Public Meeting, Discusses Future Vision, Fukushima Reconstruction and Revitalization
15 November, 2019
IAEA/RCA Symposium: Cooperating with Developing Countries Through Nuclear Science and Technology
▲TOP