Tohoku Electric Power Applies for Approval of Onagawa-1 Decommissioning Plan

On July 29, the Tohoku Electric Power Co. filed an application with the Nuclear Regulation Authority (NRA) of Japan for approval of the decommissioning plan for its Onagawa-1 Nuclear Power Plant (BWR, 524MWe, commissioned in June 1984). Also, three days earlier, on July 26, the company requested preliminary talks with Miyagi Prefecture, Onagawa Town and Ishinomaki City under nuclear safety agreements with the respective siting municipalities.

Onagawa-1 had originally been shut down in the wake of the giant earthquake that struck eastern Japan on March 11, 2011. In October 2018, Tohoku Electric Power decided to decommission the reactor after a comprehensive review of the major technological challenges involved were it to be restarted, such as measures to enhance safety, a consideration of the number of years it had been in operation, and issues related to power generation.

The entire decommissioning process is divided into four stages, as follows: (1) preparation for dismantling, (2) the dismantling and removal of facilities and equipment in the area surrounding the reactor, (3) the dismantling and removal of facilities and equipment in the reactor area, and (4) the dismantling and removal of the reactor building and other structures.

The final completion of the process is put at more than three decades from now, at FY53 (April 2053 to March 2054). During the stage of preparation for dismantling—the period from approval of the decommissioning plan to FY27—all of the 821 spent fuel assemblies currently stored in the Unit 1 spent fuel pool will be transferred to and stored in the Unit 3 spent fuel pool.

Once decommissioning is complete, the fuel assemblies will then be transferred to the licensee for reprocessing activities, together with the 161 fuel assemblies from Unit 1 that are now being stored at the spent fuel pools of Units 2 and 3.

Of the approximately 300,000 tons of dismantling waste expected as a result of the decommissioning, about 18,500 tons will be solid radioactive waste. About 12,400 tons of the latter amount is expected to be below a designated clearance level (that is, not requiring handling as radioactive material) and will be recycled to the maximum extent, following prescribed procedures under relevant laws. The total cost for dismantling is estimated at JPY41.9 billion (US$380 million at USD1=JPY110).

Additionally, of the total of 14 NPPs currently designated for decommissioning (excluding all units at Fukushima Daiichi and Daini), decommissioning plans for nine reactors have already been approved by the NRA, as follows:

  • Tokai-2 and Tsuruga-1 (Japan Atomic Power Company)
  • Hamaoka-1 and -2 (Chubu Electric Power Co.)
  • Mihama-1 and -2 (Kansai Electric Power Co.)
  • Shimane-1 (Chugoku Electric Power Co.)
  • Ikata-1 (Shikoku Electric Power Co.)
  • Genkai-1 (Kyushu Electric Power Co.)

Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

SNS facebooktwitter

NPPs Map

Video

Voices from Nuclear Industry – Contributing to a clean and resilient recovery

3 September, 2020
Voices from Nuclear Industry – Contributing to a clean and resilient recovery03:59

Recent News

24 February, 2021
FEPC Chairman Explains Response to Earthquake off Fukushima
17 February, 2021
Site for Spent Fuel Intermediate Storage Facility Outside Fukui Prefecture to Be Determined by End of 2023
5 January, 2021
New Year’s Greeting by JAIF Chairman Imai
10 December, 2020
Japan’s NRA Recognizes Compatibility of JNFL’s MOX Fuel Fabrication Plant with New Regulatory Standards, Approving Changes
3 December, 2020
MHI Launches New Strategy to Achieve Carbon Neutrality by 2050
26 November, 2020
JAIF Releases Results of Fact-finding Survey of Japanese Nuclear Industry for Fiscal 2019: Some Effects Seen of COVID-19
24 November, 2020
Japan’s Energy Supply and Demand in Fiscal 2019 Shows CO2 Emissions Down for Sixth Year in a Row
24 November, 2020
NUMO Accepts Applications from Two Municipalities to Conduct Literature Surveys, Moving Closer Toward Selecting HLW Final Disposal Site
16 November, 2020
Kyushu Electric Power Starts Operating Facilities at Sendai-1 NPP Designed for “Specific Severe Accident” Response—First Time in Japan
13 November, 2020
Japan’s NRA Approves Changes to Mutsu Recyclable-Fuel Storage Center after Confirming Regulatory Compliance
▲TOP