Home > NPPs in Japan > Fugen
NPPs in Japan
Under decommissioning
Fugen
| Age: |
24 |
| Reactor Type: |
ATR |
| Gross Output: |
165MWe |
| Owner: |
JAEA |
| Operator: |
JNC |
| Date of order: |
1967 |
| Construction Start: |
1970-12 |
| Concrete placing: |
1972-05 |
| Initial Criticality: |
1978-03-20 |
| Grid connection: |
1978-07-29 |
| Commercial Operation: |
1979-03-20 |
| Main contractor: |
various |
| Architect Engineer: |
JNC |
| Reactor System supplier: |
Hitachi |
| Reactor Vessel supplier: |
Hitachi |
| Incore Structure supplier: |
Hitachi |
| Fuel supplier: |
NFI/JNC |
| Steam raising supplier: |
Toshiba |
| Turbine generator supplier: |
Toshiba |
| Civil works: |